On October 1st, work will start on the extension project “Expansion Non-Schengen East” (UNSØ) at Avinor Oslo Airport. An information meeting will be held for contractors, and a prior information notice for the tender competitions has been published.
(Illustration: Avinor / Nordic - Office of Architecture)
(Illustration: Avinor / Nordic - Office of Architecture)

The project “Expansion Non-Schengen East” (UNSØ), Oslo Airport Phase 2 comprises construction of a building of approximately 30,000 m2 linked to the East Pier and associated fixed points and aircraft parking positions.

Construction work will start on 1 October 2018 and is scheduled to be completed in the second quarter of 2022. The total budget for the extension is NOK 3.3 billion.

Information meeting
An information meeting for suppliers regarding Project UNSØ – Expansion Non-Schengen East, Oslo Airport, will be held on Wednesday 19 September at 12.00 noon at Park Inn, Gardermoen. Interested parties must register for the information meeting by sending an email to anskaffelser_unso@avinor.no, stating the company’s name and the number of people who will be attending.

“Work on the expansion of the non-Schengen terminal area is starting in October. We are looking forward to getting started and the upcoming competitions to find the best contractors to build the new building," says Runar Botten, Avinor’s acting project director.

The information meeting will be useful for all suppliers that are interested in the project. The first contracts for the building will be announced in February 2019.
Important project for Norway
“The expansion of Oslo Airport is important to further develop Norway’s main airport as an international hub. It will provide increased capacity and improve conditions for our passengers and airlines, as well as improving the framework conditions for travel, tourism and business in Norway – which is an important part of Avinor’s social mission,” says Øyvind Hasaas. Managing Director of Avinor Oslo Airport.

The current capacity of the area for non-Schengen traffic is 5.5 million passengers per year. After the expansion, capacity will be approximately 8 million passengers per year.

“In recent years, there has been significantly greater growth in traffic to and from countries outside of the Schengen Area than in traffic within it. It is absolutely essential that we build good, adapted infrastructure to handle this traffic. This will increase Norway’s competitiveness and provide considerable economic benefits,” concludes Hasaas.

For more information about the competitions, see the prior information notice at doffin.no. (Doffin reference: 2018-432883).

Keywords

Contacts

Press contact numberPress service for journalists

Travellers are adviced to call our passenger service at +47 915 06 400

Tel:+47 918 15 614

Images

(Illustration: Avinor / Nordic - Office of Architecture)
(Illustration: Avinor / Nordic - Office of Architecture)
Download

About The Avinor Group

Avinor is a wholly-owned state limited company under the Norwegian Ministry of Transport and Communications and is responsible for 43 state-owned airports.

Avinor has taken a leading role in reducing climate gas emissions from the aviation industry, including the development of electric aircrafts and supplying sustainable jet-biojetfuel.

Avinor provides safe and efficient travels for around 50 million passengers annualy, half of which travel to and from Oslo Airport.

Over 3000 employees are responsible for planning, developing and operating an efficient airport and air navigation service. Avinor is financed via airport charges and commercial sales.  The air navigation services is organized as ​subsidiary wholly-owned by Avinor. Avinor's headquarter is in Oslo.

Subscribe to releases from The Avinor Group

Subscribe to all the latest releases from The Avinor Group by registering your e-mail address below. You can unsubscribe at any time.

Latest releases from The Avinor Group

Norway Aviation Leaders Sign LOI to Participate in an International Test Arena for Zero- and Low-Emission Aviation10.12.2024 08:00:00 CET | Press release

OSLO, Norway, December 10, 2024 — A Letter of Intent (LOI) has been signed among key aviation stakeholders to participate in an International Test Arena for Zero- and Low-Emission Aviation in Norway. This landmark agreement — which involves the Civil Aviation Authority of Norway (CAA Norway), Avinor AS, BETA Technologies, and Bristow Norway AS (a subsidiary of Bristow Group Inc.) — signifies the parties’ shared commitment to accelerating the adoption of zero- and low-emission aircraft and marks a significant step toward bringing that future to the Nordic region.

Third Quarter 2024: Framework conditions providing sufficient room for manoeuvre27.11.2024 12:15:00 CET | Press release

In November 2023, the Ministry of Transport recognized that Avinor needed significant improvements in its framework conditions to avoid extensive write-downs of assets. The government announced that it would consider a range of possible measures to be presented in the 2025 state budget proposal. In the state budget proposal, the government suggests real growth in Avinor's fees as the main tool to achieve necessary improvement in results.

In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.

Visit our pressroom
World GlobeA line styled icon from Orion Icon Library.HiddenA line styled icon from Orion Icon Library.Eye