Monument Progresses Flotation Commissioning at Selinsing
The first filtered gold concentrate produced on December 27th, 2022
VANCOUVER, British Columbia, Feb. 27, 2023 (GLOBE NEWSWIRE) -- Monument Mining Limited (TSX-V: MMY and FSE: D7Q1) ("Monument" or the "Company") is pleased to update the progress at the Selinsing Sulphide Project. With the completion of the flotation plant construction at the Selinsing Gold Mine in Malaysia, the sulphide treatment plant has been placed into commissioning after the oxide plant production ceased in mid-November 2022. The first gold concentrate was filtered on December 27, 2022 and the ramp up period commenced in January 2023.
President and CEO Cathy Zhai commented, “During commissioning we have identified some bottlenecks and are working with Mincore to fix them. Up to date the flotation plant has delivered saleable concentrate of approximately 1,707 dry tonnes at 35.12 g/t Au with gold content of 1,928 troy ounces. In the meantime, with unexpected heavy rainfall in the dry season, we also are focused on acceleration of the mining rates to fulfill commercial production requirement.”
Figure 1. Flotation Plant
To view this piece of content from ml.globenewswire.com, please give your consent at the top of this page.
Figure 2. Plant Inspection
To view this piece of content from ml.globenewswire.com, please give your consent at the top of this page.
Flotation Commissioning Progress
The commissioning stages include: (1) preparation - to confirm the completeness of construction and deliver the commissioning plan for test work, (2) dry commissioning - to test if mechanical, electrical and electronic equipment and components in the circuit are installed correctly and completely according to designed protocols and their availability, (3) wet commissioning - to test circulation of water through the flotation circuit and the plant as a whole ensure the water and pumping system up running for the designed purpose;(4) ore commissioning - to start-up with first fill to verify flotation performance and tune it to meet the designed performance in connection with front end circuit, this includes but not limited to the control level, the flows in relation to each components in the circuit and to overall treatment process, the water balance and mass balance. During the commissioning process the bottlenecks will be identified and corrected.
After the start-up ore commissioning, a ramp up period will tune the plant under increased mill feed and required conditions until commercial production is reached. The management and board would consider the commercial production is reached when the flotation plant is running for 30 days continuously with production at 85% to 90% designed capacity.
Progress Highlights
- Construction of the flotation plant completed except weighbridge and the concentrate storage shed.
- Dry and wet commissioning completed on flotation cells, concentrate and water recovery thickeners, reagents mixing and storage, blowers, compressor and filter press plant.
- Ore commissioning started on December 15th,2022 with assistance from various consulting engineers: Mincore (engineering design), Metso-Outotec (thickeners), BGRIMM (flotation cells), Powerwell (MCC), Enertech (PLC and SCADA control system), McLanahan (filter press) and ISI Control (instrumentation control).
- Ongoing improvements to flotation circuit, correcting shortfalls identified during ore commissioning period.
- Flotation plant currently operating at 90% capacity and expected ramp-up to design capacity of 119 tph in March 2023.
- As of February 22nd, 2023, a total of 1,707 dry metric tonnes of gold concentrate have been produced with an average gold grade of 35.12 g/t Au (1,928 troy ounces).
Figure 3: Operating Scada System
To view this piece of content from ml.globenewswire.com, please give your consent at the top of this page.
Figure 4: Concentrate Filter Cake Stockpile
To view this piece of content from ml.globenewswire.com, please give your consent at the top of this page.
Commissioning Technical Findings and Ramp up
As of February 22, 2023, a total of 1,707 tonnes of flotation concentrate have been produced at an average grade of 35.12 g/t Au. The flotation plant is currently operating at a mill feed rate of around 120 wet tonnes / 107 dry tonnes per hour or around 90% of design capacity. The mill feed rate will be increased over the next month with the aim of achieving and maintaining the design capacity of 119 tph by the end of March 2023.
Some bottlenecks were identified during ore commissioning period that took longer time than expected, mainly caused by design deficiencies. While temporary solutions are in place to tune the plant to reach designed protocols and production level, actions have been undertaken to receive and review redesign from Mincore.
Both the flotation concentrate and the water recovery (flotation tailings) thickeners were successfully commissioned. The performance was compromised however by design deficiencies in relation to flotation tailings management; a stilling well was installed that stabilized the tailings pump operation as a temporary solution; the revised design for a tailings hopper sent by Mincore is currently under review.
The flotation concentrate pipeline and launder were found to be undersized; a new pipeline will be installed and new launder fabricated once the design is received. The concentrate thickener underflow pump has at times struggled to deliver concentrate to the filter press surge tank and modifications to both the pump suction and delivery lines are planned. The concentrate thickener overflow delivery line was undersized; an additional bigger diameter pipeline was installed as an interim solution; bigger pumps and pipelines will be installed.
The concentrate filter press has been successfully commissioned and initial filter cake containing around 20% moisture has been produced. Filter press commissioning was assisted by the manufacturer McLanahan who had direct on-line access to the control screen. Minor adjustments have been made to the automatic control system in an effort to lower the moisture level, this has been helped to some extent by coarsening the grind size and reducing the slimes content of the flotation concentrate.
In addition to the flotation plant construction, most ancillary buildings have been completed apart from the final concentrate shed, due to start in March 2023. Mechanical installation has been completed except for the weighbridge, which is ongoing, and the bagging system that has yet to be delivered. Power and instrumentation cabling have all been installed apart from that for the concentrate shed, the weighbridge and the bagging system.
About Monument
Monument Mining Limited (TSX-V: MMY, FSE:D7Q1) is an established Canadian gold producer that 100% owns and operates the Selinsing Gold Mine in Malaysia and the Murchison Gold Project in the Murchison area of Western Australia. It has 20% interest in Tuckanarra Gold Project jointly owned with Odyssey Gold Ltd in the same region. The Company employs approximately 200 people in both regions and is committed to the highest standards of environmental management, social responsibility, and health and safety for its employees and neighboring communities.
Cathy Zhai, President and CEO
Monument Mining Limited
Suite 1580 -1100 Melville Street
Vancouver, BC V6E 4A6
FOR FURTHER INFORMATION visit the company web site at www.monumentmining.com or contact:
Richard Cushing, MMY Vancouver T: +1-604-638-1661 x102 rcushing@monumentmining.com
"Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release."
Forward-Looking Statement
This news release includes statements containing forward-looking information about Monument, its business and future plans ("forward-looking statements"). Forward-looking statements are statements that involve expectations, plans, objectives or future events that are not historical facts and include the Company's plans with respect to its mineral projects and the timing and results of proposed programs and events referred to in this news release. Generally, forward-looking information can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". The forward-looking statements in this news release are subject to various risks, uncertainties and other factors that could cause actual results or achievements to differ materially from those expressed or implied by the forward-looking statements. These risks and certain other factors include, without limitation: risks related to general business, economic, competitive, geopolitical and social uncertainties; uncertainties regarding the results of current exploration activities; uncertainties in the progress and timing of development activities; foreign operations risks; other risks inherent in the mining industry and other risks described in the management discussion and analysis of the Company and the technical reports on the Company's projects, all of which are available under the profile of the Company on SEDAR at www.sedar.com. Material factors and assumptions used to develop forward-looking statements in this news release include: expectations regarding the estimated cash cost per ounce of gold production and the estimated cash flows which may be generated from the operations, general economic factors and other factors that may be beyond the control of Monument; assumptions and expectations regarding the results of exploration on the Company's projects; assumptions regarding the future price of gold of other minerals; the timing and amount of estimated future production; the expected timing and results of development and exploration activities; costs of future activities; capital and operating expenditures; success of exploration activities; mining or processing issues; exchange rates; and all of the factors and assumptions described in the management discussion and analysis of the Company and the technical reports on the Company's projects, all of which are available under the profile of the Company on SEDAR at www.sedar.com. Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. The Company does not undertake to update any forward-looking statements, except in accordance with applicable securities laws.
Photos accompanying this announcement are available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/4ee45702-71d1-4432-af3d-ad12b70ff62f
https://www.globenewswire.com/NewsRoom/AttachmentNg/32add158-50a1-4dc0-8823-c8fbef7afea2
https://www.globenewswire.com/NewsRoom/AttachmentNg/78a97e38-02f1-46fc-ade2-66466fc9ad93
https://www.globenewswire.com/NewsRoom/AttachmentNg/c8c740c4-fd3e-4aa5-a23f-81c4ca72cfb4
To view this piece of content from www.globenewswire.com, please give your consent at the top of this page.
To view this piece of content from ml.globenewswire.com, please give your consent at the top of this page.
About GlobeNewswire by notified
GlobeNewswire by notified is one of the world's largest newswire distribution networks, specializing in the delivery of corporate press releases financial disclosures and multimedia content to the media, investment community, individual investors and the general public.
Subscribe to releases from GlobeNewswire by notified
Subscribe to all the latest releases from GlobeNewswire by notified by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from GlobeNewswire by notified
Iveco Group signs a 150 million euro term loan facility with Cassa Depositi e Prestiti to support investments in research, development and innovation11.6.2024 12:00:00 CEST | Press release
Turin, 11th June 2024. Iveco Group N.V. (EXM: IVG), a global automotive leader active in the Commercial & Specialty Vehicles, Powertrain and related Financial Services arenas, has successfully signed a term loan facility of 150 million euros with Cassa Depositi e Prestiti (CDP), for the creation of new projects in Italy dedicated to research, development and innovation. In detail, through the resources made available by CDP, Iveco Group will develop innovative technologies and architectures in the field of electric propulsion and further develop solutions for autonomous driving, digitalisation and vehicle connectivity aimed at increasing efficiency, safety, driving comfort and productivity. The financed investments, which will have a 5-year amortising profile, will be made by Iveco Group in Italy by the end of 2025. Iveco Group N.V. (EXM: IVG) is the home of unique people and brands that power your business and mission to advance a more sustainable society. The eight brands are each a
DSV, 1115 - SHARE BUYBACK IN DSV A/S11.6.2024 11:22:17 CEST | Press release
Company Announcement No. 1115 On 24 April 2024, we initiated a share buyback programme, as described in Company Announcement No. 1104. According to the programme, the company will in the period from 24 April 2024 until 23 July 2024 purchase own shares up to a maximum value of DKK 1,000 million, and no more than 1,700,000 shares, corresponding to 0.79% of the share capital at commencement of the programme. The programme has been implemented in accordance with Regulation No. 596/2014 of the European Parliament and Council of 16 April 2014 (“MAR”) (save for the rules on share buyback programmes set out in MAR article 5) and the Commission Delegated Regulation (EU) 2016/1052, also referred to as the Safe Harbour rules. Trading dayNumber of shares bought backAverage transaction priceAmount DKKAccumulated trading for days 1-25478,1001,023.01489,100,86026:3 June 20247,0001,050.597,354,13027:4 June 20245,0001,055.705,278,50028:6 June20243,0001,096.273,288,81029:7 June 20244,0001,106.174,424,68
Landsbankinn hf.: Offering of covered bonds11.6.2024 11:16:36 CEST | Press release
Landsbankinn will offer covered bonds for sale via auction held on Thursday 13 June at 15:00. An inflation-linked series, LBANK CBI 30, will be offered for sale. In connection with the auction, a covered bond exchange offering will take place, where holders of the inflation-linked series LBANK CBI 24 can sell the covered bonds in the series against covered bonds bought in the above-mentioned auction. The clean price of the bonds is predefined at 99,594. Expected settlement date is 20 June 2024. Covered bonds issued by Landsbankinn are rated A+ with stable outlook by S&P Global Ratings. Landsbankinn Capital Markets will manage the auction. For further information, please call +354 410 7330 or email verdbrefamidlun@landsbankinn.is.
Relay42 unlocks customer intelligence with a new insights and reporting module, powered by Amazon QuickSight11.6.2024 11:00:00 CEST | Press release
AMSTERDAM, June 11, 2024 (GLOBE NEWSWIRE) -- Relay42, a leading European Customer Data Platform (CDP), is leveraging Amazon QuickSight to power its new real-time customer intelligence, reporting, and dashboard module. Harnessing the breadth and quality of customer data, the new Insights module empowers marketing teams to dive deep into customer behaviors and gain invaluable insights into the performance of their marketing programs across all online, offline, paid, and owned marketing channels. Preview of the Relay42 Insights module, in pre-beta version Key capabilities of the Relay42 Insights module include: Deep insights into customer behaviors: With the Relay42 Insights module, marketers can ask unlimited questions about their data and gain a deeper understanding of how to serve their customers more effectively. Simplicity with AI-powered querying: Marketers can use artificial intelligence to query their data using natural language search, reducing the reliance on data scientists. Us
Metasphere Labs Announces X Spaces Event on the Topic of Green Bitcoin Mining and Sound Money for Sustainability11.6.2024 10:30:00 CEST | Press release
VANCOUVER, British Columbia, June 11, 2024 (GLOBE NEWSWIRE) -- Metasphere Labs Inc. (formerly Looking Glass Labs Ltd., "Metasphere Labs" or the "Company") (Cboe Canada: LABZ) (OTC: LABZF) (FRA: H1N) is thrilled to announce an engaging Twitter Spaces event on Green Bitcoin mining, energy markets, and sustainability on July 3, 2024 at 2 p.m. ET. Follow us on X at MetasphereLabs for updates and to join the event. What We'll Discuss Bitcoin Mining Basics: Understand the fundamentals of Bitcoin mining.Energy Market Dynamics: Explore how Bitcoin mining interacts with energy markets.Sustainable Innovations: Learn about our efforts to promote sustainability in Bitcoin mining.Sound Money: Discover how tamper-proof currency can enhance stability.Efficient Payment Rails: See how fast, neutral payment systems support humanitarian projects.Carbon Footprint: Compare Bitcoin's environmental impact with traditional banking. "We're excited to host this event and dive into the critical topics of Bitcoin