Maha Energy AB (publ) announce its 2021 Capital Plan and Production Guidance

Share

Maha Energy AB (“Maha” or the “Company”) expects to allocate approximately USD 26 million on capital projects during 2021 and estimates the corporate average annual production to be between 4,000 – 5,000 BOEPD*.  The 2021 Capital Plan will be funded through internal cashflows and a contemplated future financing.

The Company is pleased to provide details of its 2021 Capital Plan and Production Guidance as follows:

2021 Capital Plan Summary- Total Budget ~USD 26 Million

FieldCapital Program2021 Quarter Description/Purpose
TieNew Well
Tie-3
Q1 (ongoing)Maintain Tie field long term production plateau
TieNew Well
Tie-4 (AG HZ)
Q2Maintain Tie field long term production plateau

TieNew Well
Tie-5
Q3Maintain Tie field long term production plateau

TieFacilitiesThroughout 2021Completion of upgrade work, automation work, and tie in of new wells.
TartarugaFacilities UpgradeQ3Increasing processing capacity
IB4 New WellsQ2 –Q3Commitment wells
MafraqNoneN/APreparatory work
LAKNoneN/ANo planned investments during 2021

Tie Field - Bahia, Brazil

Tie- 2021 Capital Plan

Tie-3
Tie-3 is a dual oil producer drilled on the western flank of the Tie structure.  This well was originally planned for Q4 2020, but due to operational delays on Tie-2, this well was not started until late 2020.  This well will eventually be converted to a water injector.

Tie-4
Tie-4 is earmarked to be the field’s first horizontal well.  The well will be drilled from the GTE-4 pad and completed in the Agua Grande formation.  This well is under license review by the Brazilian authorities.  License approval is expected sometime in the 2nd quarter of 2021.

BOEPD: Barrels of Oil Equivalents Per Day

Tie-5
Tie-5 will be drilled on the southern flank of the Tie structure as a water injector to maintain reservoir pressure and increase oil recovery.

Tie Facilities
The Tie facilities are all but complete, and the capital earmarked for the Tie facilities include tie-in work (flow lines and manifolding) for the new wells.  Additional work includes automation of the plant and minor punch-list items.

Tartaruga Field – Sergipe, Brazil

Tartaruga- 2021 Capital Plan

Facility Upgrade
With the recent results from the TTG-3 well only minor work will continue during 2021 to upgrade the production facilities at Tararuga to handle up to 2,500 BOPD and 2,500 MSCFPD of gas.

LAK Ranch –Wyoming USA

LAK- 2021 Capital Plan

LAK Ranch
The LAK Ranch heavy oil field was shut in at the beginning of the Pandemic in 2020.  No work is planned for 2021 and the field will remain shut in until oil prices recover.  Whilst the Reserves valuation continues to point towards a full field development with lower but yet positive net present value, even at the current depressed oil prices, the Company maintains better yielding investments in Brazil, Illinois Basin and Oman

Illinois Basin (IB)–Illinois and Indiana, USA

IB- 2021 Capital Plan

Wells
Production will continue from the IB area during 2021.  4 wells are planned for the year, and these wells are considered to be commitment wells to keep all leases in good standing.

Mafraq Oil Field, Oman

Oman- 2021 Capital Plan

Wells
No wells are planned for 2021 in Oman – however, preparatory work will commence whereby personnel and equipment will be mobilized so that drilling can commence during 2022.

Production

The Company expects to complete most, if not all, of the Capital Plan prior to year-end 2021.  The exact timing of the operations is dependent upon a number of factors including delivery of long lead items, rig availability, permitting and logistics which in turn might affect Company’s total annual production.  Continuing effects of the Covid-19 Pandemic is expected to affect the timing of the Capital Plan and the 2021 Production Guidance.  

As such, this 2021 Production Guidance, net to the Company (but before government or freehold royalties) is expressed in the range of 4,000 – 5,000 BOEPD*, of which approximately 8% is estimated to be gas.  The guidance assumes continuing indirect effects of the Covid-19 Pandemic, such as logistical impediments due to reduced border access and depressed commodity prices.  As the global pandemic eases and restrictions are reduced, the Company expects an increase in activity which in turn may affect the production guidance positively.

The Company estimates its Operating costs for 2021 (including oil transportation costs), to range between $7 and $8 per BOE applying the production guidance range provided above.

Funding of 2021 Capital Plan

2021 Capital Plan Budget
The 2021 Capital Plan has a total budget of ~USD 26 million for the above incremental projects and is expected to be funded fully through a combination of operating cash flow and proceeds from financing.

BOEPD: Barrels of Oil Equivalents Per Day

1 Normal units for expressing gas production is m3/day or ft3/day.  An average industry conversion factor to barrels does not use a simple volumetric conversion factor from m3 (or ft3) to barrels.  Instead the energy produced by burning 1 barrel of oil is equated to the same volume of gas required to produce the same amount of energy.  This is of course dependent on the type of gas being burned, but an industry average is that 6,000 standard cubic feet (scf) of gas generate the same amount of energy as 1 barrel of oil.  As such in this and future production guidance   6,000 scf of gas will be equal to 1 barrel of oil equivalent.

Miscellaneous
The information was submitted for publication, through the agency of the contact person set out below, at 22:05 CET on February 4, 2021.

For more information, please contact:        
Jonas Lindvall (CEO)
Tel: +46 8 611 05 11        
jonas@mahaenergy.ca

Victoria Berg (Investor Relations)
Tel: +46 8 611 05 11      
victoria@mahaenergy.ca

About Maha
Maha Energy AB (publ) is a listed, international upstream oil and gas company whose business activities include exploration, development and production of crude oil and natural gas. The strategy is to target and develop underperforming hydrocarbon assets on global basis. Maha operates four oil fields: Tartaruga and Tie in Brazil, Powder River (LAK Ranch) and Illinois Basin in the United States. The shares are listed on Nasdaq Stockholm (MAHA-A). The head office is in Stockholm, Sweden with a technical office in Calgary, Canada, as well as operations offices in Grayville, Illinois, USA and Rio De Janeiro, Brazil. For more information, please visit our website www.mahaenergy.ca

Attachment

To view this piece of content from www.globenewswire.com, please give your consent at the top of this page.
To view this piece of content from ml-eu.globenewswire.com, please give your consent at the top of this page.

About GlobeNewswire by notified

GlobeNewswire by notified
GlobeNewswire by notified
One Liberty Plaza - 165 Broadway
NY 10006 New York

https://notified.com

GlobeNewswire by notified is one of the world's largest newswire distribution networks, specializing in the delivery of corporate press releases financial disclosures and multimedia content to the media, investment community, individual investors and the general public.

Subscribe to releases from GlobeNewswire by notified

Subscribe to all the latest releases from GlobeNewswire by notified by registering your e-mail address below. You can unsubscribe at any time.

Latest releases from GlobeNewswire by notified

Iveco Group signs a 150 million euro term loan facility with Cassa Depositi e Prestiti to support investments in research, development and innovation11.6.2024 12:00:00 CEST | Press release

Turin, 11th June 2024. Iveco Group N.V. (EXM: IVG), a global automotive leader active in the Commercial & Specialty Vehicles, Powertrain and related Financial Services arenas, has successfully signed a term loan facility of 150 million euros with Cassa Depositi e Prestiti (CDP), for the creation of new projects in Italy dedicated to research, development and innovation. In detail, through the resources made available by CDP, Iveco Group will develop innovative technologies and architectures in the field of electric propulsion and further develop solutions for autonomous driving, digitalisation and vehicle connectivity aimed at increasing efficiency, safety, driving comfort and productivity. The financed investments, which will have a 5-year amortising profile, will be made by Iveco Group in Italy by the end of 2025. Iveco Group N.V. (EXM: IVG) is the home of unique people and brands that power your business and mission to advance a more sustainable society. The eight brands are each a

DSV, 1115 - SHARE BUYBACK IN DSV A/S11.6.2024 11:22:17 CEST | Press release

Company Announcement No. 1115 On 24 April 2024, we initiated a share buyback programme, as described in Company Announcement No. 1104. According to the programme, the company will in the period from 24 April 2024 until 23 July 2024 purchase own shares up to a maximum value of DKK 1,000 million, and no more than 1,700,000 shares, corresponding to 0.79% of the share capital at commencement of the programme. The programme has been implemented in accordance with Regulation No. 596/2014 of the European Parliament and Council of 16 April 2014 (“MAR”) (save for the rules on share buyback programmes set out in MAR article 5) and the Commission Delegated Regulation (EU) 2016/1052, also referred to as the Safe Harbour rules. Trading dayNumber of shares bought backAverage transaction priceAmount DKKAccumulated trading for days 1-25478,1001,023.01489,100,86026:3 June 20247,0001,050.597,354,13027:4 June 20245,0001,055.705,278,50028:6 June20243,0001,096.273,288,81029:7 June 20244,0001,106.174,424,68

Landsbankinn hf.: Offering of covered bonds11.6.2024 11:16:36 CEST | Press release

Landsbankinn will offer covered bonds for sale via auction held on Thursday 13 June at 15:00. An inflation-linked series, LBANK CBI 30, will be offered for sale. In connection with the auction, a covered bond exchange offering will take place, where holders of the inflation-linked series LBANK CBI 24 can sell the covered bonds in the series against covered bonds bought in the above-mentioned auction. The clean price of the bonds is predefined at 99,594. Expected settlement date is 20 June 2024. Covered bonds issued by Landsbankinn are rated A+ with stable outlook by S&P Global Ratings. Landsbankinn Capital Markets will manage the auction. For further information, please call +354 410 7330 or email verdbrefamidlun@landsbankinn.is.

Relay42 unlocks customer intelligence with a new insights and reporting module, powered by Amazon QuickSight11.6.2024 11:00:00 CEST | Press release

AMSTERDAM, June 11, 2024 (GLOBE NEWSWIRE) -- Relay42, a leading European Customer Data Platform (CDP), is leveraging Amazon QuickSight to power its new real-time customer intelligence, reporting, and dashboard module. Harnessing the breadth and quality of customer data, the new Insights module empowers marketing teams to dive deep into customer behaviors and gain invaluable insights into the performance of their marketing programs across all online, offline, paid, and owned marketing channels. Preview of the Relay42 Insights module, in pre-beta version Key capabilities of the Relay42 Insights module include: Deep insights into customer behaviors: With the Relay42 Insights module, marketers can ask unlimited questions about their data and gain a deeper understanding of how to serve their customers more effectively. Simplicity with AI-powered querying: Marketers can use artificial intelligence to query their data using natural language search, reducing the reliance on data scientists. Us

Metasphere Labs Announces X Spaces Event on the Topic of Green Bitcoin Mining and Sound Money for Sustainability11.6.2024 10:30:00 CEST | Press release

VANCOUVER, British Columbia, June 11, 2024 (GLOBE NEWSWIRE) -- Metasphere Labs Inc. (formerly Looking Glass Labs Ltd., "Metasphere Labs" or the "Company") (Cboe Canada: LABZ) (OTC: LABZF) (FRA: H1N) is thrilled to announce an engaging Twitter Spaces event on Green Bitcoin mining, energy markets, and sustainability on July 3, 2024 at 2 p.m. ET. Follow us on X at MetasphereLabs for updates and to join the event. What We'll Discuss Bitcoin Mining Basics: Understand the fundamentals of Bitcoin mining.Energy Market Dynamics: Explore how Bitcoin mining interacts with energy markets.Sustainable Innovations: Learn about our efforts to promote sustainability in Bitcoin mining.Sound Money: Discover how tamper-proof currency can enhance stability.Efficient Payment Rails: See how fast, neutral payment systems support humanitarian projects.Carbon Footprint: Compare Bitcoin's environmental impact with traditional banking. "We're excited to host this event and dive into the critical topics of Bitcoin

World GlobeA line styled icon from Orion Icon Library.HiddenA line styled icon from Orion Icon Library.Eye