Highlights:

•     9m 2020 total gold productionamounted to 755 kg (24,285 oz), compared to 481 kg (15,467 oz) in 9m 2019, an increase of 57%, or 274 kg (8,818 oz). Hard rock gold production at Tardan increased from 430 kg (13,812 oz) in 9m 2019 to 750 kg (24,112 oz) in 9m 2020, or by 75%;

•     9m 2020 gold sales amounted to 757 kg (24,322 oz), compared to 426 kg (13,696 oz) in 9m 2019, an increase of 331 kg (10,642 oz), or 78%;

•     Volume of ore processed through the newly built CIL plant amounted to 291 thousand tonnes with an average grade of 2.77 g/t (total gold in processed ore – 806 kg);

•     The CIL plant was operating at projected throughput per working hour (>50 t/hour) and higher recovery rate (92.9%);

•     Heap leach operations were discontinued at the end of December, 2019;

•     Ore mined amounted to 274 thousand tonnes (18% less than in the same period of the previous year). Stripping volume in 9m 2020 was 684 thousand m3 (12% less than in 9m 2019);

•     The average grade in ore mined in 9m 2020 was 2.47 g/t, as compared to 2.38 g/t in 9m 2019, an increase of 4%;

•     Gold production at Solcocon amounted to 5 kg, as compared to 51 kg in the same period of the previous year. It is expected to produce 10-12 kg at Solcocon this year. The reduction in production is due to the late start of mining operations because of the corona virus.

Production

Production unitQ3 2020Q3 2019Change9m 20209m 2019Change
kgozkgozkgoz%kgozkgozkgoz%
Hard rock
  Tardan (heap leach)202  6,504  (202)  (6,504)  (100%)430  13,812  (430)  (13,812)  (100%)
  Tardan (CIL)229  7,363  229  7,363  0%750  24,112  750  24,112  0%
Alluvial
  Solcocon172  24  775  (19)  (602)  (78%)172  51  1,655  (46)  (1,482)  (90%)
Total gold produced234  7,535  226  7,279  256  4%755  24,285  481  15,467  274  8,818  57%

Tardan

UnitQ3 2020Q3 2020Change9m 20209m 2019Change
Mining
Waste stripping000 m3255  261  (6)  (2%)684  776  (92)  (12%)
Ore mined000 tonnes122  143  (21)  (15%)274  333  (59)  (18%)
Gold in Orekg304  304  0%676  793  (116)  (15%)
Average gradeg/t2.49  2.12  0.37  17%2.47  2.38  0.09  4%
Heap leach
Ore stacking000 tonnes134  (134)  (100%)307  (307)  (100%)
Gradeg/t0.00  1.97  (1.97)  (100%)0.00  2.11  (2.11)  (100%)
Gold in ore stackedkg263  (263)  (100%)648  (648)  (100%)
Gold produced HLkg202  (202)  (100%)430  (430)  (100%)
CIL
Ore processing000 tonnes95  95  0%291  291  0%
Gradeg/t2.58  0.00  2.58  0%2.77  0.00  2.77  0%
Gold in ore processingkg245  245  0%806  806  0%
Gold produced CILkg229  229  0%750  750  0%
Gold produced totalkg229  202  27  13%750  430  320  75%
Warehouse on Seprember 30
Ore000 tonnes91  29  62  217%91  29  62  217%
Gradeg/t2.02  5.31  (3.29)  (62%)2.02  5.31  (3.29)  (62%)

For more information please contact:

Danilo Lange, CEO
Tel: +7 495 109 02 82
E-mail: d.lange@auriant.com

Company name: Auriant Mining AB Short name: AUR
ISIN-code: SE0001337213

Website: www.auriant.com
www.facebook.com/AuriantMining/

Auriant Mining AB (AUR) is a Swedish junior mining company focused on gold exploration and production in Russia, primarily in Zabaikalye and the Republics of Khakassia and Tyva. The company has currently four assets, including two operating mines (Tardan and Solcocon), one early stage exploration asset and one development asset.

Since July 19, 2010, Auriant Mining´s shares are traded on Nasdaq First North Premier Growth Market under the short name AUR. For more information please visit www.auriant.com. Mangold Fondkommission is Certified Adviser to Auriant, for more information please call +46 8 503 015 50, e-mail CA@mangold.se or visit www.mangold.se.

This information is information that Auriant Mining AB is obliged to make public pursuant to the EU Market Abuse Regulation. The information was submitted for publication, through the agency of the contact persons set out above, at 17.45 CET on October 19th , 2020.

Cautionary Statement: Statements and assumptions made in this report with respect to Auriant Mining AB’s (“AUR”) current plans, estimates, strategies and beliefs, and other statements that are not historical facts, are forward-looking statements about the future performance of AUR. Forward-looking statements include, but are not limited to, those using words such as "may", "might", "seeks", "expects", "anticipates", "estimates", "believes", "projects", "plans", strategy", "forecast" and similar expressions. These statements reflect management's expectations and assumptions in light of currently available information. They are subject to a number of risks and uncertainties, including, but not limited to, (i) changes in the economic, regulatory and political environments in the countries where AUR operates; (ii) changes relating to the geological information available in respect of the various projects undertaken; (iii) AUR’s continued ability to secure enough financing to carry on its operations as a going concern; (iv) the success of its potential joint ventures and alliances, if any; (v) exchange rates, particularly between the Russian rouble and the U.S. dollar. In the light of the many risks and uncertainties surrounding any gold production and exploration company at an early stage of its development, the actual results could differ materially from those presented and forecast in this report. AUR assumes no unconditional obligation to immediately update any such statements and/or forecasts. This press release shall not, directly or indirectly, be released, published or distributed in or to the United States, Australia Japan, Canada, New Zealand, Hong Kong, South Africa or other country where such action as a whole or in part is subject to legal restrictions. Nothing in this press release should be considered as an offer to invest or otherwise trade in shares of Auriant Mining AB (publ). The proposed issue will not be directed at residents or those living in the United States, Australia, Japan, Canada, New Zealand, Hong Kong, South Africa or other country where such action would require further prospectus, other offering documentation, registration or other measures beyond those required by Swedish law. No securities will be registered under the United States Securities Act of 1933, a similar law in any state in the United States, or under any provincial law in Canada, nor under the applicable law of another country.

Attachment

About GlobeNewswire

GlobeNewswire
GlobeNewswire
One Liberty Plaza - 165 Broadway
NY 10006 New York

https://globenewswire.com

GlobeNewswire is one of the world's largest newswire distribution networks, specializing in the delivery of corporate press releases financial disclosures and multimedia content to the media, investment community, individual investors and the general public.

Subscribe to releases from GlobeNewswire

Subscribe to all the latest releases from GlobeNewswire by registering your e-mail address below. You can unsubscribe at any time.

Latest releases from GlobeNewswire

Touax: Success of the partial buyback of the Undated Deeply Subordinated Bond27.11.2020 17:45:00 CETPress release

PRESS RELEASE Paris, November 27, 2020 – 5.45 p.m. YOUR OPERATIONAL LEASING SOLUTION FOR SUSTAINABLE TRANSPORTATION Success of the partial buyback of the Undated Deeply Subordinated Bond Touax SCA announces today that it has bought back and canceled part of the Undated Deeply Subordinated Bond issued in August 2013, November 2013 and May 2014, for a nominal amount of 24.2 million euros. The outstanding amount of the bonds stands at 26.6 million euros. This operation will enable to optimize the capital structure of the Group and to lower the related costs. Fabrice and Raphaël Walewski, managing partners of Touax Group commented: “The strategic refocusing initiated since 2018 around the long-term rental business of environmentally-friendly transport equipment has allowed a return to growth and profit over the first half of 2020. The capital increase of Touax Rail for 81.9 million euros achieved at the end of September 2020 significantly strengthened the capital of the Rail division and t

CONDITIONS FOR RIKSBANK REVERSED AUCTIONS SEK MUNICIPAL BONDS27.11.2020 16:20:00 CETPress release

Anbudsförfarande kommuner och regioner, 2020-12-01BondsFixed rate notes issued in SEK by Municipalities or Regions with maturity in: 2025 The following issuers are accepted for delivery: Göteborgs Stad Jönköpings Kommun Malmö Stad Nacka Kommun Region Skåne Stockholms Stad Region Stockholm Vellinge Kommun Västerås Stad Delivery may not be made in Bonds purchased by the Counterparty from the issuer less than one week prior to the date for announcing the Specific terms, i.e. the purchase may not have been made after: 2020-11-20BidsBids are made to tel 08-696 69 70 and confirmed in writing by a filled-in Bid form by e-mail to EOL@riksbank.se Bid date2020-12-01Bid times10.00-11.00 (CET/CEST) on the Bid dateRequested volume (corresponding nominal amount)SEK 750 +/- 750 millionHighest permitted bid volume (corresponding nominal amount)The total bid volume from one Counterparty for the two Credit rating classes may not exceed SEK 1 000 million. No bid may contain Bonds exceeding SEK 750 millio

CONDITIONS FOR PURCHASES OF CORPORATE BONDS27.11.2020 16:20:00 CETPress release

Bid procedure, 2020-12-02BondsBonds issued in SEK by Swedish non-financial undertakings. The following bonds are eligible for delivery: VASAKRONAN AB: XS1941844174, 2022-02-11 VASAKRONAN AB: XS2051470552, 2024-09-11 HEMSO FASTIGHETS AB: XS1876163103, 2022-03-07 HEMSO FASTIGHETS AB: XS1938445530, 2021-10-22 VOLVO TREASURY AB: XS2153414292, 2022-12-08 VOLVO TREASURY AB: XS2018763461, 2021-06-28 HUSQVARNA AB: SE0009664543, 2022-03-01 HUSQVARNA AB: SE0010869669, 2023-02-14 AB INDUSTRIVARDEN: SE0011869668, 2022-02-28 AB INDUSTRIVARDEN: SE0012676724, 2023-02-20 Delivery of a Bond may not occur if the Counterparty has purchased the Bond from the issuer more recently than one month prior to the date of announcement of the Special terms, that is, the purchase may not have taken place after: 2020-11-02Bid date2020-12-02Bid times10.00-11.00 (CET/CEST) on the Bid dateRequested volume (corresponding nominal amount)XS1941844174: 30 mln SEK +/-30 mln SEK XS2051470552: 30 mln SEK +/-30 mln SEK XS18761

CONDITIONS FOR RIKSBANK REVERSED AUCTIONS SEK COVERED BONDS27.11.2020 16:20:00 CETPress release

Bid procedure, 2020-12-03BondsSTADSHYPOTEK AB: 1590, SE0012676690, 2025-09-03 SWEDBANK HYPOTEK AB: 194, SE0012142206, 2024-09-18 NORDEA HYPOTEK AB: 5535, SE0013358413, 2025-09-17 SKANDINAVISKA ENSKILDA: 580, SE0013101722, 2025-12-17 LANSFORSAKRINGAR HYPOTEK: 518, SE0011309244, 2025-09-17 DANSKE HYPOTEK AB: 2512, SE0013877214, 2025-12-17 SWEDISH COVERED BOND: 146, SE0013381571, 2025-06-11 Bid date2020-12-03Bid times09.00-10.00 (CET/CEST) on the Bid dateRequested volume (corresponding nominal amount)1590: 1200 mln SEK +/-600 mln SEK 194: 1000 mln SEK +/-500 mln SEK 5535: 1000 mln SEK +/-500 mln SEK 580: 800 mln SEK +/-400 mln SEK 518: 600 mln SEK +/-300 mln SEK 2512: 300 mln SEK +/-150 mln SEK 146: 600 mln SEK +/-300 mln SEK Maximum 5500 mln in totalHighest permitted bid volume (corresponding nominal amount)1590: 1200 mln SEK per bid 194: 1000 mln SEK per bid 5535: 1000 mln SEK per bid 580: 800 mln SEK per bid 518: 600 mln SEK per bid 2512: 300 mln SEK per bid 146: 600 mln SEK per bid Lo

CONDITIONS FOR RIKSBANK REVERSED AUCTIONS SEK GOVERNMENT BONDS27.11.2020 16:20:00 CETPress release

Bid procedure, 2020-12-04BondsSWEDEN I/L BOND: 3108, SE0004211084, 2022-06-01 SWEDEN I/L BOND: 3109, SE0005703550, 2025-06-01 Bid date2020-12-04Bid times09.00-10.00 (CET/CEST) on the Bid dateRequested volume (corresponding nominal amount)3108: 500 mln SEK +/-250 mln SEK 3109: 500 mln SEK +/-250 mln SEK Maximum 1000 mln in totalHighest permitted bid volume (corresponding nominal amount)3108: 500 mln SEK per bid 3109: 500 mln SEK per bid Lowest permitted bid volume (corresponding nominal amount)SEK 50 million per bidExpected allocation timeNo later than 10.10 (CET/CEST) on the Bid dateDelivery and payment date2020-12-08Delivery of bondsTo the Riksbank's account in Euroclear Sweden AB's securities settlement system 1 4948 6383 Stockholm, 2020-11-27 This is a translation of the special terms and conditions published on www.riksbank.se. In the case of any inconsistency between the English translation and the Swedish language version, the Swedish language version shall prevail. Complete term

Greenfield cement project in Ethiopia is effective27.11.2020 15:45:28 CETPress release

Company Announcement No. 21 -2020, 3 November 2020 The previously announced signed contract for engineering, procurement and supervision on a cement plant in Ethiopia (Company Announcement No. 1-2019 on 24 January 2019) with Abay Industrial Development Share Company, is now effective. Located near the city of Dejen in Ethiopia, the new greenfield plant will play an important role for the development of local infrastructure. Once fully operational the plant will have a capacity of 5,000 tonnes per day and creating more than 300 new jobs in the area. The contract is valued at around EUR 100 million. The order includes design and engineering, full equipment supply, automation systems, installation and commissioning as well as training and extended supervision. Key deliveries are expected to commence towards the end of 2021. The majority of revenue from this project is expected in the subsequent years. “We are happy to see the contract now in effect,” said Carsten Riisberg Lund, President,