Green data centers supply heat for the Dielsdorf and Regensdorf region
20.11.2026 09:07:50 CET | news aktuell GmbH | Press release
The first apartments in Dielsdorf are now being heated with waste heat from Green data centers. Energie 360° is officially commissioning the new energy center today. In the future, up to 11,500 households as well as industrial and commercial businesses will benefit in six municipalities.

Lupfig, November 19, 2026 – Companies run their servers and IT systems in Green’s data centers in Dielsdorf. The heat generated in the process is then systematically reused: Green recovers the heat and makes it available for use. Ever since the data centers were commissioned, their waste heat has been used on campus and in a neighboring industrial enterprise. Now, for the first time, it is also being used in residential buildings. Energie 360° has built an energy center on the campus that treats the waste heat for the heat supply and has set up an extensive district heating network.
The heating network is being expanded in stages, with the lines to Regensdorf already under construction. Once fully developed, the district heating network is expected to supply up to 11,500 households, as well as industrial and commercial businesses in Dielsdorf, Niederhasli, Steinmaur, Regensdorf, Buchs, and Dällikon, with climate-friendly heat for space heating and hot water. “The waste heat from the Green data centers allows us to replace fossil-fuel heating systems with a local heat source. We are thus driving the development of the climate-friendly heat supply in the region,” says Walter Ineichen, Head of Grid Solutions at Energie 360°.
Data centers as part of an efficient energy system
Green is dedicated to the resource-efficient operation of its data centers, with energy-efficient cooling systems that use outdoor air for cooling, closed cooling circuits with no water consumption and the targeted use of waste heat. The technical prerequisites for heat extraction were already put in place when the campus was planned.
In addition to the efficient use of energy, Green is also contributing to the stability of the power supply. If required, the emergency power systems in the data center can provide tertiary balancing energy to support the Swiss electricity grid. Green obtains the energy for its operational infrastructure from renewable sources.
“Data centers are part of the future of energy. We want to use energy as efficiently as possible and integrate our infrastructure into the energy system in a meaningful way. In Dielsdorf, the waste heat from our data centers becomes heating energy for the region. This is what the circular economy looks like in practice,” says Roger Süess, CEO of Green.
Images can be downloaded here.
https://www.green.ch/en/about-green/news-media/download-area
Contacts
Green’s media office:medien@green.ch
Tel:+41 56 460 23 80Images
About Green
Green is the leading data center provider in Switzerland. The company currently operates seven data centers in the greater Zurich area, with two more under construction. Further projects in Switzerland and Germany are in the planning stages. By building secure, high-availability and energy-efficient data center capacities, Green is laying the foundation for networked and powerful IT, cloud and AI environments for large companies and cloud providers. Green is the only Swiss provider to have the “M&O Stamp of Approval” for operational excellence from the Uptime Institute and has received multiple awards, including as a Swiss market leader for data centers and colocation, and for innovation in waste heat utilization and energy efficiency.
Find out more at www.green.ch
Subscribe to releases from news aktuell GmbH
Subscribe to all the latest releases from news aktuell GmbH by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from news aktuell GmbH
Neato expands exchange programme for customers across Europe19.11.2026 13:35:39 CET | Press release
Wuppertal, 19 November 2026 – Neato Robotics is significantly expanding its exchange programme for Neato customers across Europe, with the support of the Vorwerk Group. The programme is available to eligible private customers who purchased a Neato robot after 1 October 2020.
Advanced Robotics Conference 2026: FEV highlights pathways to industrial deployment of Physical AI19.11.2026 11:00:00 CET | Press release
Aachen, Germany, November 2026 – The Advanced Robotics Conference (ARC) 2026 will bring together leading representatives from international technology companies, start-ups, and research institutions at FEV’s headquarters in Aachen, Germany, on November 25 and 26. The event will focus on the latest technological developments, specific fields of application, and the prerequisites for the widespread adoption of advanced robotics.
Broermann Medical Innovation Award 2026: Three Pioneers of Modern Obesity and Diabetes Therapies Honored17.11.2026 16:00:00 CET | Press release
Prof. Svetlana Mojsov, Prof. Dr. Richard DiMarchi, and Prof. Dr. Dr. h.c. Matthias H. Tschöp honored for groundbreaking research on metabolic diseases and obesity therapies. Minister-President Boris Rhein presents the medical award, endowed with a total of one million euros, at the Hessian State Chancellery. Titia große Broermann: " this year’s laureates powerfully demonstrate how scientific curiosity sparks medical progress that can transform millions of lives”
PARACELSUS MEDICAL UNIVERSITY: PHARMACY PROGRAM GOES INTERNATIONAL16.11.2026 09:00:00 CET | Press release
Starting in the fall of 2027, the “Pharmacy and Pharmaceutical Sciences” program will be the first English-taught pharmacy program in the German-speaking region to qualify students to work across a range of pharmacy roles and settings.
Infomaniak and Gruyère Energie develop a data center project in Bulle designed to limit its footprint13.11.2026 13:41:04 CET | Press release
Geneva and Bulle, 13 November 2026 – Infomaniak SA (SIX: INFO), a Swiss cloud provider, and Gruyère Energie SA announce that the planning application for a data center in Bulle will be put on public display on 13 November. Planned for 2028, this next-generation facility is intended to meet growing digital needs while reusing the heat produced by its servers in the existing district heating network. Its planned IT capacity of 2.5 megawatts (MW) is twice that of Infomaniak’s most recent data center, in Geneva. The project remains modest in size.
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom