Equinox Gold Receives Positive Record of Decision for South Railroad; Significant Permitting Milestone Unlocks Next North American Growth Project
17.8.2026 12:00:00 CEST | GlobeNewswire by notified | Press release
VANCOUVER, British Columbia, Aug. 17, 2026 (GLOBE NEWSWIRE) -- Equinox Gold Corp. (TSX: EQX, NYSE American: EQX) (“Equinox Gold” or the “Company”) is pleased to announce that the United States Bureau of Land Management (“BLM”) has issued a positive Record of Decision (“ROD”) for the South Railroad project in Nevada, USA (“South Railroad” or the “Project”), marking completion of federal permitting under the National Environmental Policy Act (NEPA) process.
With the ROD now issued, early works construction at South Railroad has begun. Applications for key state permits and water rights have also been submitted.
Jason Simpson, President of Equinox Gold, commented: “Receiving the Record of Decision is a major milestone for the South Railroad project and advances our next phase of growth. The incremental production from South Railroad will be the first meaningful contributor towards our objective of adding 800,000 ounces of annual gold production from our organic development pipeline. Our Board of Directors had previously approved the start of construction, and with the Record of Decision now in hand, South Railroad is positioned for first gold production in 2028. We thank the Bureau of Land Management, Secretary of the Interior Burgum, the U.S. Administration, and the Permitting Council for their support of the Project, including its designation as a FAST-41 covered project, and for their commitment to responsible domestic mineral development.”
South Railroad will be an open-pit heap leach mine. Based on the 2026 feasibility study, the Project is expected to produce an average 130,000 ounces of gold annually over the first five years of operation, and more than 100,000 ounces annually over the initial 10-year mine life. Initial capital costs are estimated at $395 million, including $70-$80 million reflected in Equinox Gold’s updated 2026 Guidance. The Project is situated within a larger 25,000-hectare land package along Nevada’s prolific Carlin Trend, which provides opportunities for resource growth and new discoveries.
Construction Milestones for Remainder of 2026
Several key construction milestones targeted for completion this year include:
- Workforce ramp-up: As part of operational readiness, hiring and onboarding of site operations team are advancing through the second half of this year.
- Detailed engineering: Engineering is 55.2% complete.
- Ordering and procurement: Major contracts for power generation, process plant equipment, concrete and structural steel have been awarded.
- Construction acceleration: Early works commenced earlier this summer on the north access road outside of the BLM Plan of Operations in coordination with Elko County, Nevada. Earthworks and major civil construction activities have commenced following the receipt of the ROD.
- Equipment: Mining equipment will begin arriving on site at year-end, with initial mining activities scheduled to start in spring 2027.
AboutEquinoxGold
Equinox Gold (TSX: EQX, NYSE-A: EQX) is a Canadian mining company positioned as the new North American senior gold producer with a strong foundation of high-quality, long-life gold operations in Canada and across the Americas, and a pipeline of development and expansion projects. Guided by a seasoned leadership team with broad expertise, the Company is focused on disciplined execution, operational excellence and long-term value creation. Equinox Gold offers investors meaningful exposure to gold with a diversified portfolio and clear path to growth. Learn more at www.equinoxgold.com or contact ir@equinoxgold.com.
EquinoxGold Contact
Etienne Morin, Chief Capital Markets Officer
E: etienne.morin@equinoxgold.com
T: +1 604.260.0516
Ingrid Rico, SVP Capital Markets
E: ingrid.rico@equinoxgold.com
T: +1 604.260.0516
Qualified Person and Technical Information
The scientific and technical information contained in this news release was approved by Andrew Cormier, Chief Operating Officer for Equinox Gold and a “Qualified Person” under National Instrument 43-101.
For additional information regarding the South Railroad Project, please refer to the technical report titled “South Railroad Project NI 43-101 Feasibility Study Update, Elko County, Nevada” dated February 27, 2026, with an effective date of September 30, 2025, which is available on the Company’s website at www.equinoxgold.com.
CautionaryNotes&Forward-LookingStatements
This news release includes forward-looking information and forward-looking statements within the meaning of applicable securities laws andmayincludefuture-orientedfinancialinformationorfinancialoutlookinformation(collectively“Forward-lookingInformation”).Actualresultsofoperations and the ensuing financial results may vary materially from the amounts set out in any Forward-looking Information. Forward-lookingInformation in this news release includes: timing and receipt of key state permits and water rights; the Company’s target of 800,000 ounces of additional annual gold production from its development portfolio; timing of first gold; estimates for annual production from South Railroad; initial capital costs for South Railroad; construction and mining milestones for South Railroad; and the prospectivity of the Company’s land package at South Railroad. Forward-looking Information is typically identified by words such as “believe”, “will”, “grow”, “plan”, “expect”,“estimate”, “advance”, “commence”, “continue” and similar terms, including variations like “may”, “could”, or “should”, or the negative connotation of suchterms. While the Company believes these expectations are reasonable, they are not guarantees and undue reliance should not be placed onthis Forward-Looking information. Forward-looking Information is based on the Company’s current expectations and assumptions, including: receipt and timing thereof of required state permits and water rights to commence South Railroad development; timing and progress of construction, engineering, and procurement;; achievement of exploration,production, cost and development objectives; stablegoldpricesandinputcosts in line with the assumptions utilized in the estimation of Mineral Reserves and Mineral Resources;;accuracyofMineralReserveandMineralResourceestimates; availability of funding; adherencetomineplansandschedules;expectedoregradesandrecoveries;absenceoflabourdisruptions, supply chain disruptions, regulatory delays, legal challenges,or otherunplanneddelays; productive relationships with workers, unions and communities; maintenance and timely receipt of permits and regulatory approvals;compliance with environmental and safety regulations; optimized operating assumptions and technical parameters, and constructive engagement with community partners.While theCompany considers these assumptions reasonable, they may prove incorrect.Forward-looking Information involves numerous risks,uncertainties and other factors that may cause actual results and developments to differ materially from those expressed or implied by such Forward-looking Information. Such factors include certain risks and uncertainties described in the section “Risk Factors” in Equinox Gold’s Management Information Circular dated June 19, 2026, and in the section “Risks Related to the Business” in Equinox Gold’s most recently filed Annual Information Form, each of which is available on SEDAR+ at www.sedarplus.ca and on EDGAR at www.sec.gov/edgar. Forward-looking Information reflects management’s current expectations for future events and is subject to change. Except as required by applicable law, the Company assumes no obligation to update or to publicly announce the results of any change to any Forward-looking Information contained or incorporated by reference to reflect actual results, future events or developments, changes in assumptions or other factors affecting Forward-looking Information. If the Company updates any Forward-looking Information, no inference should be drawn that the Company will make additional updates with respect to those or other Forward-looking Information. All Forward-looking Information contained in this news release is expressly qualified by this cautionary statement.
Subscribe to releases from GlobeNewswire by notified
Subscribe to all the latest releases from GlobeNewswire by notified by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from GlobeNewswire by notified
Iveco Group signs a 150 million euro term loan facility with Cassa Depositi e Prestiti to support investments in research, development and innovation11.6.2024 12:00:00 CEST | Press release
Turin, 11th June 2024. Iveco Group N.V. (EXM: IVG), a global automotive leader active in the Commercial & Specialty Vehicles, Powertrain and related Financial Services arenas, has successfully signed a term loan facility of 150 million euros with Cassa Depositi e Prestiti (CDP), for the creation of new projects in Italy dedicated to research, development and innovation. In detail, through the resources made available by CDP, Iveco Group will develop innovative technologies and architectures in the field of electric propulsion and further develop solutions for autonomous driving, digitalisation and vehicle connectivity aimed at increasing efficiency, safety, driving comfort and productivity. The financed investments, which will have a 5-year amortising profile, will be made by Iveco Group in Italy by the end of 2025. Iveco Group N.V. (EXM: IVG) is the home of unique people and brands that power your business and mission to advance a more sustainable society. The eight brands are each a
DSV, 1115 - SHARE BUYBACK IN DSV A/S11.6.2024 11:22:17 CEST | Press release
Company Announcement No. 1115 On 24 April 2024, we initiated a share buyback programme, as described in Company Announcement No. 1104. According to the programme, the company will in the period from 24 April 2024 until 23 July 2024 purchase own shares up to a maximum value of DKK 1,000 million, and no more than 1,700,000 shares, corresponding to 0.79% of the share capital at commencement of the programme. The programme has been implemented in accordance with Regulation No. 596/2014 of the European Parliament and Council of 16 April 2014 (“MAR”) (save for the rules on share buyback programmes set out in MAR article 5) and the Commission Delegated Regulation (EU) 2016/1052, also referred to as the Safe Harbour rules. Trading dayNumber of shares bought backAverage transaction priceAmount DKKAccumulated trading for days 1-25478,1001,023.01489,100,86026:3 June 20247,0001,050.597,354,13027:4 June 20245,0001,055.705,278,50028:6 June20243,0001,096.273,288,81029:7 June 20244,0001,106.174,424,68
Landsbankinn hf.: Offering of covered bonds11.6.2024 11:16:36 CEST | Press release
Landsbankinn will offer covered bonds for sale via auction held on Thursday 13 June at 15:00. An inflation-linked series, LBANK CBI 30, will be offered for sale. In connection with the auction, a covered bond exchange offering will take place, where holders of the inflation-linked series LBANK CBI 24 can sell the covered bonds in the series against covered bonds bought in the above-mentioned auction. The clean price of the bonds is predefined at 99,594. Expected settlement date is 20 June 2024. Covered bonds issued by Landsbankinn are rated A+ with stable outlook by S&P Global Ratings. Landsbankinn Capital Markets will manage the auction. For further information, please call +354 410 7330 or email verdbrefamidlun@landsbankinn.is.
Relay42 unlocks customer intelligence with a new insights and reporting module, powered by Amazon QuickSight11.6.2024 11:00:00 CEST | Press release
AMSTERDAM, June 11, 2024 (GLOBE NEWSWIRE) -- Relay42, a leading European Customer Data Platform (CDP), is leveraging Amazon QuickSight to power its new real-time customer intelligence, reporting, and dashboard module. Harnessing the breadth and quality of customer data, the new Insights module empowers marketing teams to dive deep into customer behaviors and gain invaluable insights into the performance of their marketing programs across all online, offline, paid, and owned marketing channels. Preview of the Relay42 Insights module, in pre-beta version Key capabilities of the Relay42 Insights module include: Deep insights into customer behaviors: With the Relay42 Insights module, marketers can ask unlimited questions about their data and gain a deeper understanding of how to serve their customers more effectively. Simplicity with AI-powered querying: Marketers can use artificial intelligence to query their data using natural language search, reducing the reliance on data scientists. Us
Metasphere Labs Announces X Spaces Event on the Topic of Green Bitcoin Mining and Sound Money for Sustainability11.6.2024 10:30:00 CEST | Press release
VANCOUVER, British Columbia, June 11, 2024 (GLOBE NEWSWIRE) -- Metasphere Labs Inc. (formerly Looking Glass Labs Ltd., "Metasphere Labs" or the "Company") (Cboe Canada: LABZ) (OTC: LABZF) (FRA: H1N) is thrilled to announce an engaging Twitter Spaces event on Green Bitcoin mining, energy markets, and sustainability on July 3, 2024 at 2 p.m. ET. Follow us on X at MetasphereLabs for updates and to join the event. What We'll Discuss Bitcoin Mining Basics: Understand the fundamentals of Bitcoin mining.Energy Market Dynamics: Explore how Bitcoin mining interacts with energy markets.Sustainable Innovations: Learn about our efforts to promote sustainability in Bitcoin mining.Sound Money: Discover how tamper-proof currency can enhance stability.Efficient Payment Rails: See how fast, neutral payment systems support humanitarian projects.Carbon Footprint: Compare Bitcoin's environmental impact with traditional banking. "We're excited to host this event and dive into the critical topics of Bitcoin