Aduro Clean Technologies Provides Update on NGP Pilot Plant Commissioning
30.10.2025 12:00:00 CET | GlobeNewswire by notified | Press release
LONDON, Ontario, Oct. 30, 2025 (GLOBE NEWSWIRE) -- Aduro Clean Technologies Inc. (“Aduro” or the “Company”) (Nasdaq: ADUR) (CSE: ACT) (FSE: 9D5), a clean technology company using the power of chemistry to transform lower value feedstocks, like waste plastics, heavy bitumen, and renewable oils, into resources for the 21st century, today provides an update on the progress of the Next Generation Process (NGP) Pilot Plant.
Highlights of Ongoing Commissioning Progress
- On-schedule progression: The NGP Pilot Plant remains on schedule, having advanced from Phase 1 to Phase 2 commissioning as planned.
- Commissioning of core systems underway: All major modules, including the extruder, Zeton-fabricated process skids, and Siemens automation network, are now installed at the London, Ontario facility and are progressing through staged commissioning.
- System validation milestones achieved: The extruder successfully completed Site Acceptance Testing (SAT); Zeton skids passed Factory Acceptance Testing (FAT); and Siemens is continuing work on automation system commissioning alongside physical equipment.
- Phase 2 commissioning focus: Current activities include sequential testing, subsystem verification, wet runs, and process tuning through November and into mid-December 2025, preparing the plant for integrated operation.
- Operator training and procedures: Commissioning activities also include planned operator training and development of standardized operating procedures, ensuring readiness for continuous plant operation and future scale-up phases.
The NGP Pilot Plant is a key step in the Company’s scale-up pathway, designed to validate Hydrochemolytic™ Technology in continuous operation, establish operating parameters across target feedstocks, and produce product samples and quality data for customer evaluation. It will confirm mass and energy balances, yields, and controllability, supply data to support environmental assessments and lifecycle analyses, support operator training and procedures, and generate the key data to inform the design basis and integration approach for the previously announced demonstration plant with an initial capacity of 8,000 tons per year.
All three main systems are now onsite at the recently expanded Aduro laboratory facilities in London, Ontario, and commissioning has advanced into its next phase. Since the last project update, the NGP Pilot Plant moved from Phase 1 into Phase 2 commissioning. Phase 1, which began in September 2025, focused on assembly and installation of major systems, mechanical completion, and verification of utilities and communications. During this period, the extruder system was installed, commissioned, and successfully completed its Site Acceptance Test (SAT). The modular process skids fabricated by Zeton Inc. also completed Factory Acceptance Testing (FAT) prior to shipment and have since been delivered to site. Siemens Canada completed configuration of the automation, control, and communication systems, and integrated the extruder systems, utilities, and ancillary systems into an integrated control network. Additional work included connection of plant utilities, electrical systems, and safety interlocks, ensuring full readiness for process commissioning. Assembly and integration activities continue as the plant progresses through Phase 2 commissioning.
The commissioning roadmap continues to follow a structured progression. Phase 2 commissioning, which began in October 2025, focuses on integrated operations, wet runs, and process tuning. These activities will continue through November and into mid-December, after which the Pilot Plant will move toward final preparation for extended operation campaigns.
Key partners of Aduro continue to play a central role in supporting the commissioning phase. Zeton Inc., the engineering, and fabrication partner that completed and delivered the modular process skids, remains actively engaged during integration and commissioning. Siemens Canada installed the plant’s automation and control systems and is supporting calibration and validation to ensure reliable process performance and proper data acquisition. These coordinated efforts provide the framework for a safe and efficient start-up.
“This milestone underscores the progress of Team Aduro,” said Ofer Vicus, Chief Executive Officer of Aduro. “The NGP Pilot Plant represents the first-in-kind implementation of our Hydrochemolytic™ Technology, and seeing it move from construction into commissioning is deeply rewarding for everyone involved. This milestone reflects the dedication and collaboration across our operations, research, and senior leadership teams, people who have worked with relentless focus to bring us to this point. The data and experience gained during this process will provide critical insight into system performance, feedstock segregation, environmental footprint, and continuous improvement, all of which will inform the design, fabrication, and commissioning of our Demonstration Plant and bring us closer to commercialization. We are also grateful to our partners, Zeton and Siemens, whose expertise and collaboration have been instrumental in achieving this progress.”
“The Pilot Plant represents a complex integration of equipment and process systems, and I am very pleased with the coordinated effort across engineering, operations, and safety teams,” added David Weizenbach, Chief Operating Officer of Aduro. “As we progress through phase 2 commissioning, our focus remains on verifying performance, ensuring reliability, and completing operator training so that we enter the next stage of operation with confidence.”
About Aduro Clean Technologies
Aduro Clean Technologies is a developer of patented water-based technologies to chemically recycle waste plastics; convert heavy crude and bitumen into lighter, more valuable oil; and transform renewable oils into higher-value fuels or renewable chemicals. The Company’s Hydrochemolytic™ technology relies on water as a critical agent in a chemistry platform that operates at relatively low temperatures and cost, a game-changing approach that converts low-value feedstocks into resources for the 21st century.
For further information, please contact:
Abe Dyck, Head of Corporate Development / Investor Relations
ir@adurocleantech.com
+1 226 784 8889
KCSA Strategic Communications
Jack Perkins, Senior Vice President
aduro@kcsa.com
Forward-Looking Statements
This news release contains forward-looking statements within the meaning of applicable securities laws. All statements other than statements of historical fact may be forward-looking statements. Forward-looking statements are often, but not always, identified by words such as “expects,” “anticipates,” “believes,” “intends,” “estimates,” “potential,” “plans,” “projects,” “targets,” “forecasts,” “may,” “will,” “should,” or similar expressions.
In this news release, forward-looking statements include, but are not limited to, statements relating to the progress, timing, and objectives of the Pilot Plant Program, the advancement of Phase 2 commissioning and subsequent validation activities, anticipated outcomes from extended operation campaigns, and the expected development, design, and timing of the Demonstration Plant.
These forward-looking statements are based on assumptions and estimates made by the Company in light of its experience and its perception of historical trends, current conditions, and expected future developments. Such statements are subject to a number of known and unknown risks, uncertainties, and other factors that could cause actual results or events to differ materially from those expressed or implied by such forward-looking statements. These factors include, but are not limited to, risks related to technology development, operational execution, supply chain logistics, regulatory approvals, financing availability, and other risks as described in the Company’s filings with Canadian securities regulators and the U.S. Securities and Exchange Commission.
Readers are cautioned not to place undue reliance on forward-looking statements. The Company does not undertake to update any forward-looking statements, except as required by applicable securities laws.
A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/c9d915d2-99b6-44db-ac3f-a73da989e142
Subscribe to releases from GlobeNewswire by notified
Subscribe to all the latest releases from GlobeNewswire by notified by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from GlobeNewswire by notified
Iveco Group signs a 150 million euro term loan facility with Cassa Depositi e Prestiti to support investments in research, development and innovation11.6.2024 12:00:00 CEST | Press release
Turin, 11th June 2024. Iveco Group N.V. (EXM: IVG), a global automotive leader active in the Commercial & Specialty Vehicles, Powertrain and related Financial Services arenas, has successfully signed a term loan facility of 150 million euros with Cassa Depositi e Prestiti (CDP), for the creation of new projects in Italy dedicated to research, development and innovation. In detail, through the resources made available by CDP, Iveco Group will develop innovative technologies and architectures in the field of electric propulsion and further develop solutions for autonomous driving, digitalisation and vehicle connectivity aimed at increasing efficiency, safety, driving comfort and productivity. The financed investments, which will have a 5-year amortising profile, will be made by Iveco Group in Italy by the end of 2025. Iveco Group N.V. (EXM: IVG) is the home of unique people and brands that power your business and mission to advance a more sustainable society. The eight brands are each a
DSV, 1115 - SHARE BUYBACK IN DSV A/S11.6.2024 11:22:17 CEST | Press release
Company Announcement No. 1115 On 24 April 2024, we initiated a share buyback programme, as described in Company Announcement No. 1104. According to the programme, the company will in the period from 24 April 2024 until 23 July 2024 purchase own shares up to a maximum value of DKK 1,000 million, and no more than 1,700,000 shares, corresponding to 0.79% of the share capital at commencement of the programme. The programme has been implemented in accordance with Regulation No. 596/2014 of the European Parliament and Council of 16 April 2014 (“MAR”) (save for the rules on share buyback programmes set out in MAR article 5) and the Commission Delegated Regulation (EU) 2016/1052, also referred to as the Safe Harbour rules. Trading dayNumber of shares bought backAverage transaction priceAmount DKKAccumulated trading for days 1-25478,1001,023.01489,100,86026:3 June 20247,0001,050.597,354,13027:4 June 20245,0001,055.705,278,50028:6 June20243,0001,096.273,288,81029:7 June 20244,0001,106.174,424,68
Landsbankinn hf.: Offering of covered bonds11.6.2024 11:16:36 CEST | Press release
Landsbankinn will offer covered bonds for sale via auction held on Thursday 13 June at 15:00. An inflation-linked series, LBANK CBI 30, will be offered for sale. In connection with the auction, a covered bond exchange offering will take place, where holders of the inflation-linked series LBANK CBI 24 can sell the covered bonds in the series against covered bonds bought in the above-mentioned auction. The clean price of the bonds is predefined at 99,594. Expected settlement date is 20 June 2024. Covered bonds issued by Landsbankinn are rated A+ with stable outlook by S&P Global Ratings. Landsbankinn Capital Markets will manage the auction. For further information, please call +354 410 7330 or email verdbrefamidlun@landsbankinn.is.
Relay42 unlocks customer intelligence with a new insights and reporting module, powered by Amazon QuickSight11.6.2024 11:00:00 CEST | Press release
AMSTERDAM, June 11, 2024 (GLOBE NEWSWIRE) -- Relay42, a leading European Customer Data Platform (CDP), is leveraging Amazon QuickSight to power its new real-time customer intelligence, reporting, and dashboard module. Harnessing the breadth and quality of customer data, the new Insights module empowers marketing teams to dive deep into customer behaviors and gain invaluable insights into the performance of their marketing programs across all online, offline, paid, and owned marketing channels. Preview of the Relay42 Insights module, in pre-beta version Key capabilities of the Relay42 Insights module include: Deep insights into customer behaviors: With the Relay42 Insights module, marketers can ask unlimited questions about their data and gain a deeper understanding of how to serve their customers more effectively. Simplicity with AI-powered querying: Marketers can use artificial intelligence to query their data using natural language search, reducing the reliance on data scientists. Us
Metasphere Labs Announces X Spaces Event on the Topic of Green Bitcoin Mining and Sound Money for Sustainability11.6.2024 10:30:00 CEST | Press release
VANCOUVER, British Columbia, June 11, 2024 (GLOBE NEWSWIRE) -- Metasphere Labs Inc. (formerly Looking Glass Labs Ltd., "Metasphere Labs" or the "Company") (Cboe Canada: LABZ) (OTC: LABZF) (FRA: H1N) is thrilled to announce an engaging Twitter Spaces event on Green Bitcoin mining, energy markets, and sustainability on July 3, 2024 at 2 p.m. ET. Follow us on X at MetasphereLabs for updates and to join the event. What We'll Discuss Bitcoin Mining Basics: Understand the fundamentals of Bitcoin mining.Energy Market Dynamics: Explore how Bitcoin mining interacts with energy markets.Sustainable Innovations: Learn about our efforts to promote sustainability in Bitcoin mining.Sound Money: Discover how tamper-proof currency can enhance stability.Efficient Payment Rails: See how fast, neutral payment systems support humanitarian projects.Carbon Footprint: Compare Bitcoin's environmental impact with traditional banking. "We're excited to host this event and dive into the critical topics of Bitcoin