CALGARY, Alberta, Sept. 12, 2023 (GLOBE NEWSWIRE) -- Prospera Energy Inc. (“Prospera” or the “Company”) (TSX.V: PEI, OTC: GXRFF, FRA: OF6B, OF6B.SG, OF6B.F, OF6B.BE).

To view this piece of content from ml.globenewswire.com, please give your consent at the top of this page.

Prospera has completed the drilling of four horizontal wells of the ten well multi-pad infill drill program. These wells encountered structure and pay as expected with excellent oil show throughout the pay. The drilling technique tweaked from the pilot wells were executed efficiently and ahead of schedule. High praises to Lasso Drilling Corporation for the effective synergy with Prospera to attain efficiency. These drilled horizontals are being completed and tied-in to existing infrastructure. Turnaround time to bring the production online is approximately two to three weeks; two horizontal wells are already completed. The production will be brought on gently initially to optimize recovery due to the heavier fluid properties. The full deliverability can be attained, approximately, over a three-month period. The next set of four horizontals are to commence within one week, barring any weather-related delays.

This multi-pad infill drill program stems from a comprehensive geological, seismic, and reservoir management delineation. The infill program is designed to optimize recovery with optimum wells in a cost-effective manner, while also aligning with planned enhanced and improved recovery techniques. As previously announced, this ten well program can approximately add an additional 750 bpd at a low decline to Prospera’s current 900+boepd. This infill development is intended to accelerate production and recovery to capture the significant remaining heavy oil reserves (400 million bbls).

The medium-light oil spud will follow the heavy oil horizontal well transformation from vertical wells in the latter part of this month. These slanted drills are awaiting the preparation of the new leases, surface facilities, and connecting pipelines. The medium-light oil development entails six to eight directional wells that can add an additional 600bpd (gross) at 50%, WI diversifying Prospera’s product mix and improving margin.

Overall, this Phase 2 development plan will allow Prospera Energy to become a low-cost producer with a significant increase in production. Restructured Prospera primary focus subsequent to increased production and corresponding revenue is to address all legacy arrears (especially, land owners & local community vendors), stay current with payables, and maintain services with comparable terms. Meanwhile, PEI will continue to execute its liability management plan to reduce the asset reduction obligations.

Interest Payable Reduction Settlement

PEI announces that the Corporation has accrued indebtedness to the Corporation’s convertible debenture holders (the “Creditors”) in the amount of $376,050.76 (the “Debt”) for interest expenses. The Corporation has the option to pay Creditors interest in either cash or in shares at market price, at the Corporation’s discretion, and has agreed to settle the Debt by the issuance of fully paid common shares in the capital of the Corporation (“Common Shares”).

This interest payable will reduce the current liabilities, in turn further improving its current ratio and liabilities related to the settlement of historical arrears. The Corporation intends to settle the Debt at a price per Common Share of $0.105, for an aggregate amount of 3,581,434 Common Shares. The common shares will be subject to a four-month hold period. The transaction is subject to the approval of the TSX Venture Exchange.

About Prospera Energy Inc.

Prospera Energy Inc. (TSX.V: PEI, OTC: GXRFF, FRA: OF6B) is a publicly traded energy company based in Western Canada, specializing in the exploration, development, and production of crude oil and natural gas. Prospera Energy Inc. has announced a mid-August spud of PEI’s phase 2 restructured development program intended to increase production. The phase 2 development entails the drilling of 10 horizontal wells in heavy oil and 8 slanted wells in medium-light oil to accelerate growth and capture the significant remaining reserves (400 million bbls). These horizontal laterals and slanted wells will allow PEI to increase production by approximately 1,000bpd with recovery of approximately 100Mstb per well. PEI will reduce its environmental and surface footprint by eliminating the numerous vertical well leases along the lateral path. Phase III of Prospera’s corporate redevelopment strategy will focus on continuing the company’s horizontal modular development to appreciate production and optimize recovery of remaining reserves.

Prospera intends to implement full-scale EOR applications based on the results of its Phase II pilot program, which is forecasted to optimize recovery by greater than 10%. Prospera also intends to continue its acquisition strategy to diversify its product mix. Its goal is to attain 50% light oil, 40% heavy oil and 10% gas.

PEI continues to apply efforts to minimize its environmental footprint. Also, efforts to reduce and eventually eliminate emissions, alongside pursuing innovative ESG methods to enhance API quality, thereby achieving higher margins and eliminating the need for diluents.

For further information, please contact:

Shawn Mehler, PR
shawn@prosperaenergy.com
www.prosperaenergy.com

FORWARD-LOOKING STATEMENTS
This news release contains forward-looking statements relating to the future operations of the Corporation and other statements that are not historical facts. Forward-looking statements are often identified by terms such as “will,” “may,” “should,” “anticipate,” “expects” and similar expressions. All statements other than statements of historical fact included in this release, including, without limitation, statements regarding future plans and objectives of the Corporation, are forward-looking statements that involve risks and uncertainties. There can be no assurance that such statements will prove to be accurate and actual results and future events could differ materially from those anticipated in such statements.

Although Prospera believes that the expectations and assumptions on which the forward-looking statements are based are reasonable, undue reliance should not be placed on the forward-looking statements because Prospera can give no assurance that they will prove to be correct. Since forward-looking statements address future events and conditions, by their very nature they involve inherent risks and uncertainties. Actual results could differ materially from those currently anticipated due to a number of factors and risks. These include, but are not limited to, risks associated with the oil and gas industry in general (e.g., operational risks in development, exploration and production; delays or changes in plans with respect to exploration or development projects or capital expenditures; the uncertainty of reserve estimates; the uncertainty of estimates and projections relating to production, costs and expenses, and health, safety and environmental risks), commodity price and exchange rate fluctuations and uncertainties resulting from potential delays or changes in plans with respect to exploration or development projects or capital expenditures.

The reader is cautioned that assumptions used in the preparation of any forward-looking information may prove to be incorrect. Events or circumstances may cause actual results to differ materially from those predicted, as a result of numerous known and unknown risks, uncertainties, and other factors, many of which are beyond the control of Prospera. As a result, Prospera cannot guarantee that any forward-looking statement will materialize, and the reader is cautioned not to place undue reliance on any forward- looking information. Such information, although considered reasonable by management at the time of preparation, may prove to be incorrect and actual results may differ materially from those anticipated. Forward-looking statements contained in this news release are expressly qualified by this cautionary statement. Th forward-looking statements contained in this news release are made as of the date of this news release, and Prospera does not undertake any obligation to update publicly or to revise any of the included forward-looking statements, whether as a result of new information, future events or otherwise, except as expressly required by Canadian securities law.

Neither the TSXV nor its Regulation Services Provider (as that term is defined in the policies of the TSXV) accepts responsibility for the adequacy or accuracy of this release.

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/cb97d755-cbd4-4073-b783-26a2979c3486

To view this piece of content from www.globenewswire.com, please give your consent at the top of this page.
To view this piece of content from ml.globenewswire.com, please give your consent at the top of this page.

About GlobeNewswire by notified

GlobeNewswire by notified
GlobeNewswire by notified
One Liberty Plaza - 165 Broadway
NY 10006 New York

https://notified.com

GlobeNewswire by notified is one of the world's largest newswire distribution networks, specializing in the delivery of corporate press releases financial disclosures and multimedia content to the media, investment community, individual investors and the general public.

Subscribe to releases from GlobeNewswire by notified

Subscribe to all the latest releases from GlobeNewswire by notified by registering your e-mail address below. You can unsubscribe at any time.

Latest releases from GlobeNewswire by notified

Iveco Group signs a 150 million euro term loan facility with Cassa Depositi e Prestiti to support investments in research, development and innovation11.6.2024 12:00:00 CEST | Press release

Turin, 11th June 2024. Iveco Group N.V. (EXM: IVG), a global automotive leader active in the Commercial & Specialty Vehicles, Powertrain and related Financial Services arenas, has successfully signed a term loan facility of 150 million euros with Cassa Depositi e Prestiti (CDP), for the creation of new projects in Italy dedicated to research, development and innovation. In detail, through the resources made available by CDP, Iveco Group will develop innovative technologies and architectures in the field of electric propulsion and further develop solutions for autonomous driving, digitalisation and vehicle connectivity aimed at increasing efficiency, safety, driving comfort and productivity. The financed investments, which will have a 5-year amortising profile, will be made by Iveco Group in Italy by the end of 2025. Iveco Group N.V. (EXM: IVG) is the home of unique people and brands that power your business and mission to advance a more sustainable society. The eight brands are each a

DSV, 1115 - SHARE BUYBACK IN DSV A/S11.6.2024 11:22:17 CEST | Press release

Company Announcement No. 1115 On 24 April 2024, we initiated a share buyback programme, as described in Company Announcement No. 1104. According to the programme, the company will in the period from 24 April 2024 until 23 July 2024 purchase own shares up to a maximum value of DKK 1,000 million, and no more than 1,700,000 shares, corresponding to 0.79% of the share capital at commencement of the programme. The programme has been implemented in accordance with Regulation No. 596/2014 of the European Parliament and Council of 16 April 2014 (“MAR”) (save for the rules on share buyback programmes set out in MAR article 5) and the Commission Delegated Regulation (EU) 2016/1052, also referred to as the Safe Harbour rules. Trading dayNumber of shares bought backAverage transaction priceAmount DKKAccumulated trading for days 1-25478,1001,023.01489,100,86026:3 June 20247,0001,050.597,354,13027:4 June 20245,0001,055.705,278,50028:6 June20243,0001,096.273,288,81029:7 June 20244,0001,106.174,424,68

Landsbankinn hf.: Offering of covered bonds11.6.2024 11:16:36 CEST | Press release

Landsbankinn will offer covered bonds for sale via auction held on Thursday 13 June at 15:00. An inflation-linked series, LBANK CBI 30, will be offered for sale. In connection with the auction, a covered bond exchange offering will take place, where holders of the inflation-linked series LBANK CBI 24 can sell the covered bonds in the series against covered bonds bought in the above-mentioned auction. The clean price of the bonds is predefined at 99,594. Expected settlement date is 20 June 2024. Covered bonds issued by Landsbankinn are rated A+ with stable outlook by S&P Global Ratings. Landsbankinn Capital Markets will manage the auction. For further information, please call +354 410 7330 or email verdbrefamidlun@landsbankinn.is.

Relay42 unlocks customer intelligence with a new insights and reporting module, powered by Amazon QuickSight11.6.2024 11:00:00 CEST | Press release

AMSTERDAM, June 11, 2024 (GLOBE NEWSWIRE) -- Relay42, a leading European Customer Data Platform (CDP), is leveraging Amazon QuickSight to power its new real-time customer intelligence, reporting, and dashboard module. Harnessing the breadth and quality of customer data, the new Insights module empowers marketing teams to dive deep into customer behaviors and gain invaluable insights into the performance of their marketing programs across all online, offline, paid, and owned marketing channels. Preview of the Relay42 Insights module, in pre-beta version Key capabilities of the Relay42 Insights module include: Deep insights into customer behaviors: With the Relay42 Insights module, marketers can ask unlimited questions about their data and gain a deeper understanding of how to serve their customers more effectively. Simplicity with AI-powered querying: Marketers can use artificial intelligence to query their data using natural language search, reducing the reliance on data scientists. Us

Metasphere Labs Announces X Spaces Event on the Topic of Green Bitcoin Mining and Sound Money for Sustainability11.6.2024 10:30:00 CEST | Press release

VANCOUVER, British Columbia, June 11, 2024 (GLOBE NEWSWIRE) -- Metasphere Labs Inc. (formerly Looking Glass Labs Ltd., "Metasphere Labs" or the "Company") (Cboe Canada: LABZ) (OTC: LABZF) (FRA: H1N) is thrilled to announce an engaging Twitter Spaces event on Green Bitcoin mining, energy markets, and sustainability on July 3, 2024 at 2 p.m. ET. Follow us on X at MetasphereLabs for updates and to join the event. What We'll Discuss Bitcoin Mining Basics: Understand the fundamentals of Bitcoin mining.Energy Market Dynamics: Explore how Bitcoin mining interacts with energy markets.Sustainable Innovations: Learn about our efforts to promote sustainability in Bitcoin mining.Sound Money: Discover how tamper-proof currency can enhance stability.Efficient Payment Rails: See how fast, neutral payment systems support humanitarian projects.Carbon Footprint: Compare Bitcoin's environmental impact with traditional banking. "We're excited to host this event and dive into the critical topics of Bitcoin

World GlobeA line styled icon from Orion Icon Library.HiddenA line styled icon from Orion Icon Library.Eye