VANCOUVER, British Columbia, Jan. 05, 2023 (GLOBE NEWSWIRE) -- Fortuna Silver Mines Inc. (NYSE: FSM) (TSX: FVI) reports that its Mexican subsidiary, Compania Minera Cuzcatlan (“Minera Cuzcatlan”), has received written notice of a resolution (the “SEMARNAT Resolution”) issued by the Secretaria de Medio Ambiente y Recursos Naturales (“SEMARNAT”) which provides that SEMARNAT is re-assessing the 12-year extension (“EIA Extension”) to the environmental impact authorization (“EIA”) for the San Jose Mine, located in Oaxaca, Mexico that it granted to Minera Cuzcatlan in December 2021 (refer to Fortuna news release dated December 20, 2021).

Jorge A. Ganoza, President and CEO, commented, “It is incomprehensible that we find ourselves again having to contest a controversial resolution issued by SEMARNAT. This specific authorization, one of the many under which San Jose operates, was confirmed by the Federal Court last November, with a ruling in our favor against SEMARNAT.” Mr. Ganoza added, “Moreover, under the four years of the current Mexican Administration, the San Jose Mine has been audited annually by the Federal Environmental Attorney’s Office (PROFEPA) as well as the National Water Commission (CONAGUA), and in every single audit, San Jose’s compliance with environmental obligations has been confirmed. Further, during this period, SEMARNAT has issued two multi-year environmental authorizations for the mine and tailings facility.” Mr. Ganoza concluded, “Minera Cuzcatlan is diligently working with the government authorities to resolve this matter and is concurrently pursuing all pertinent legal protection.”

Subsequent to the grant of the EIA Extension on December 16, 2021, SEMARNAT suggested that it had made a typographical error in the EIA Extension and that the correct term was two years (refer to Fortuna news release dated February 4, 2022). Minera Cuzcatlan initiated legal proceedings to challenge and revoke the alleged typographical error, and on November 7, 2022, the Company announced that the Mexican Federal Administrative Court had issued a judgment in favour of the Company and re-confirmed the term of the EIA Extension for the San Jose Mine for a period of 12 years (Refer to Fortuna Q3 2022 MD&A).

On January 2, 2023, Minera Cuzcatlan received the SEMARNAT Resolution which annuls the EIA Extension and requires SEMARNAT to re-assess its decision to extend the EIA by conducting a review of the following two areas of the extension that it previously considered, and subsequently issue a new decision related to the extension of the EIA that:

  • SEMARNAT did not have authority to grant an extension to the EIA for more than half of the original 12-year term of the EIA
  • In the EIA Extension, SEMARNAT did not provide sufficient analysis to justify the compliance by the Company of some of its environmental obligations in order for SEMARNAT to grant the extension of the term of the EIA

Management of the Company believes that the SEMARNAT Resolution is unfounded and has no merits, as:

(i)SEMARNAT has the authority under the General Ecological Equilibrium and Environmental Protection Law to grant an extension of the EIA for a period of 12 years
(ii)By granting the extension to the EIA in December 2021, SEMARNAT had confirmed that operations at the San Jose Mine are conducted in compliance with all environmental obligations under the EIA which justified the EIA Extension 

As a result, Minera Cuzcatlan will pursue all legal protection available to it, which includes initiating legal proceedings against SEMARNAT to contest and revoke the annulment of the EIA, which revocation is appealable by the Company.  

Minera Cuzcatlan is in full compliance with all material environmental laws and continues to operate under the terms of the EIA. The Company continues to work with communities from the surrounding area in relation to the mine to enhance and expand the social benefits of the mine in the region. The mine is the single largest employer in the region of Valles Centrales and provides direct employment to over 1,200 people. The Company has sustainable development initiatives with various neighbouring communities and works with over 150 small local enterprises.

About Fortuna Silver Mines Inc.

Fortuna Silver Mines Inc. is a Canadian precious metals mining company with four operating mines in Argentina, Burkina Faso, Mexico and Peru, and a fifth mine under construction in Côte d'Ivoire. Sustainability is integral to all our operations and relationships. We produce gold and silver and generate shared value over the long-term for our stakeholders through efficient production, environmental protection, and social responsibility. For more information, please visit our website.

ON BEHALF OF THE BOARD

Jorge A. Ganoza
President, CEO, and Director
Fortuna Silver Mines Inc.

Trading symbols: NYSE: FSM | TSX: FVI

Investor Relations:
Carlos Baca | info@fortunasilver.com | Twitter: @Fortuna_Silver | LinkedIn: fortunasilvermines

Forward-looking Statements

This news release contains forward-looking statements which constitute "forward-looking information" within the meaning of applicable Canadian securities legislation and "forward-looking statements" within the meaning of the "safe harbor" provisions of the United States Private Securities Litigation Reform Act of 1995 (collectively, "Forward-looking Statements"). All statements included herein, other than statements of historical fact, are Forward-looking Statements and are subject to a variety of known and unknown risks and uncertainties which could cause actual events or results to differ materially from those reflected in the Forward-looking Statements. The Forward-looking Statements in this news release include, without limitation, statements about the legal proceedings to be initiated by Minera Cuzcatlan to contest and revoke the annulment of the EIA; the likelihood of success in the legal proceedings; the Company’s business strategy, plans and outlook; the merit of the Company’s mines and mineral properties; the future financial or operating performance of the Company; expenditures; approvals and other matters. Often, but not always, these Forward-looking Statements can be identified by the use of words such as "estimated", “expected”, “intended”, “anticipated”, "potential", "open", "future", "assumed", "projected", "used", "detailed", "has been", "gain", "planned", "reflecting", "will", "containing", "remaining", "to be", or statements that events, "could" or "should" occur or be achieved and similar expressions, including negative variations.

Forward-looking Statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any results, performance or achievements expressed or implied by the Forward-looking Statements. Such uncertainties and factors include, among others, factors beyond our control, including but not limited to, the ability of Minera Cuzcatlan to successfully contest and revoke the SEMARNAT Resolution; changes in laws, rules or regulations and other challenges discussed in our public filings; changes in general economic conditions and financial markets; the continued rising rates of global inflation which impact the costs of operations; the risks relating to a global pandemic, including the COVID-19 pandemic, as well as risks associated with war or other geo-political hostilities, such as the Ukrainian – Russian conflict, any of which could continue to cause a disruption in global economic activity; fluctuation in currencies and foreign exchange rates; the imposition of capital controls in countries in which the Company operates; the continuance of currency controls in Argentina; changes in the prices of key supplies; technological and operational hazards in Fortuna’s mining and mine development activities; risks inherent in mineral exploration; uncertainties inherent in the estimation of mineral reserves, mineral resources, and metal recoveries; changes to current estimates of mineral reserves and resources; changes to production and cost estimates; changes in the position of regulatory authorities with respect to the granting of approvals or permits; governmental and other approvals; changes in government, political unrest or instability in countries where Fortuna is active; labor relations issues; as well as those factors discussed under “Risk Factors” in the Company's Annual Information Form. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in Forward-looking Statements, there may be other factors that cause actions, events or results to differ from those anticipated, estimated or intended.

Forward-looking Statements contained herein are based on the assumptions, beliefs, expectations and opinions of management, including but not limited to that the Company will be successful in revoking the SEMARNAT Resolution;that the Company’s activities will be conducted in accordance with the Company’s public statements and stated goals; that there will be no material adverse change affecting the Company, its properties or changes to production estimates (which assume accuracy of projected ore grade, mining rates, recovery timing, and recovery rate estimates and may be impacted by unscheduled maintenance, labor and contractor availability and other operating or technical difficulties); the duration and impacts of COVID-19 and other geo-political uncertainties on the Company’s production, workforce, business, operations and financial condition; the expected trends in mineral prices and currency exchange rates; that the Company will be successful in mitigating the impact of inflation on its business and operations; that all required approvals and permits will be obtained for the Company’s business and operations on acceptable terms; that there will be no significant disruptions affecting the Company's operations and such other assumptions as set out herein. Forward-looking Statements are made as of the date hereof and the Company disclaims any obligation to update any Forward-looking Statements, whether as a result of new information, future events or results or otherwise, except as required by law. There can be no assurance that these Forward-looking Statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, investors should not place undue reliance on Forward-looking Statements.

To view this piece of content from www.globenewswire.com, please give your consent at the top of this page.
To view this piece of content from ml.globenewswire.com, please give your consent at the top of this page.

About GlobeNewswire by notified

GlobeNewswire by notified
GlobeNewswire by notified
One Liberty Plaza - 165 Broadway
NY 10006 New York

https://notified.com

GlobeNewswire by notified is one of the world's largest newswire distribution networks, specializing in the delivery of corporate press releases financial disclosures and multimedia content to the media, investment community, individual investors and the general public.

Subscribe to releases from GlobeNewswire by notified

Subscribe to all the latest releases from GlobeNewswire by notified by registering your e-mail address below. You can unsubscribe at any time.

Latest releases from GlobeNewswire by notified

Iveco Group signs a 150 million euro term loan facility with Cassa Depositi e Prestiti to support investments in research, development and innovation11.6.2024 12:00:00 CEST | Press release

Turin, 11th June 2024. Iveco Group N.V. (EXM: IVG), a global automotive leader active in the Commercial & Specialty Vehicles, Powertrain and related Financial Services arenas, has successfully signed a term loan facility of 150 million euros with Cassa Depositi e Prestiti (CDP), for the creation of new projects in Italy dedicated to research, development and innovation. In detail, through the resources made available by CDP, Iveco Group will develop innovative technologies and architectures in the field of electric propulsion and further develop solutions for autonomous driving, digitalisation and vehicle connectivity aimed at increasing efficiency, safety, driving comfort and productivity. The financed investments, which will have a 5-year amortising profile, will be made by Iveco Group in Italy by the end of 2025. Iveco Group N.V. (EXM: IVG) is the home of unique people and brands that power your business and mission to advance a more sustainable society. The eight brands are each a

DSV, 1115 - SHARE BUYBACK IN DSV A/S11.6.2024 11:22:17 CEST | Press release

Company Announcement No. 1115 On 24 April 2024, we initiated a share buyback programme, as described in Company Announcement No. 1104. According to the programme, the company will in the period from 24 April 2024 until 23 July 2024 purchase own shares up to a maximum value of DKK 1,000 million, and no more than 1,700,000 shares, corresponding to 0.79% of the share capital at commencement of the programme. The programme has been implemented in accordance with Regulation No. 596/2014 of the European Parliament and Council of 16 April 2014 (“MAR”) (save for the rules on share buyback programmes set out in MAR article 5) and the Commission Delegated Regulation (EU) 2016/1052, also referred to as the Safe Harbour rules. Trading dayNumber of shares bought backAverage transaction priceAmount DKKAccumulated trading for days 1-25478,1001,023.01489,100,86026:3 June 20247,0001,050.597,354,13027:4 June 20245,0001,055.705,278,50028:6 June20243,0001,096.273,288,81029:7 June 20244,0001,106.174,424,68

Landsbankinn hf.: Offering of covered bonds11.6.2024 11:16:36 CEST | Press release

Landsbankinn will offer covered bonds for sale via auction held on Thursday 13 June at 15:00. An inflation-linked series, LBANK CBI 30, will be offered for sale. In connection with the auction, a covered bond exchange offering will take place, where holders of the inflation-linked series LBANK CBI 24 can sell the covered bonds in the series against covered bonds bought in the above-mentioned auction. The clean price of the bonds is predefined at 99,594. Expected settlement date is 20 June 2024. Covered bonds issued by Landsbankinn are rated A+ with stable outlook by S&P Global Ratings. Landsbankinn Capital Markets will manage the auction. For further information, please call +354 410 7330 or email verdbrefamidlun@landsbankinn.is.

Relay42 unlocks customer intelligence with a new insights and reporting module, powered by Amazon QuickSight11.6.2024 11:00:00 CEST | Press release

AMSTERDAM, June 11, 2024 (GLOBE NEWSWIRE) -- Relay42, a leading European Customer Data Platform (CDP), is leveraging Amazon QuickSight to power its new real-time customer intelligence, reporting, and dashboard module. Harnessing the breadth and quality of customer data, the new Insights module empowers marketing teams to dive deep into customer behaviors and gain invaluable insights into the performance of their marketing programs across all online, offline, paid, and owned marketing channels. Preview of the Relay42 Insights module, in pre-beta version Key capabilities of the Relay42 Insights module include: Deep insights into customer behaviors: With the Relay42 Insights module, marketers can ask unlimited questions about their data and gain a deeper understanding of how to serve their customers more effectively. Simplicity with AI-powered querying: Marketers can use artificial intelligence to query their data using natural language search, reducing the reliance on data scientists. Us

Metasphere Labs Announces X Spaces Event on the Topic of Green Bitcoin Mining and Sound Money for Sustainability11.6.2024 10:30:00 CEST | Press release

VANCOUVER, British Columbia, June 11, 2024 (GLOBE NEWSWIRE) -- Metasphere Labs Inc. (formerly Looking Glass Labs Ltd., "Metasphere Labs" or the "Company") (Cboe Canada: LABZ) (OTC: LABZF) (FRA: H1N) is thrilled to announce an engaging Twitter Spaces event on Green Bitcoin mining, energy markets, and sustainability on July 3, 2024 at 2 p.m. ET. Follow us on X at MetasphereLabs for updates and to join the event. What We'll Discuss Bitcoin Mining Basics: Understand the fundamentals of Bitcoin mining.Energy Market Dynamics: Explore how Bitcoin mining interacts with energy markets.Sustainable Innovations: Learn about our efforts to promote sustainability in Bitcoin mining.Sound Money: Discover how tamper-proof currency can enhance stability.Efficient Payment Rails: See how fast, neutral payment systems support humanitarian projects.Carbon Footprint: Compare Bitcoin's environmental impact with traditional banking. "We're excited to host this event and dive into the critical topics of Bitcoin

World GlobeA line styled icon from Orion Icon Library.HiddenA line styled icon from Orion Icon Library.Eye