New Bodø Airport given go ahead

The cost for Avinor’s development project is NOK 7.2 billion at 2022 prices, not including the purchase of land and excluding financing costs. This afternoon, Avinor Group’s Board of Directors approved Avinor’s financial contribution to the project in the amount of NOK 2.6 billion. The remainder will be funded by the government and by local funds.
“We are pleased to make this decision following a lengthy process that has involved the Norwegian Armed Forces and the municipality of Bodø. We are going to build a new airport, and the urban development project will have a major impact on the entire region,” says Abraham Foss, CEO of Avinor.
Long and winding path to a final decision
He makes no secret of the fact that the process to reach today’s decision has been challenging for Avinor. In January of this year, the Board resolved to postpone its decision due to several reasons, including the company’s financial following the pandemic. Avinor’s loss of income because of COVID-19 in the period 2020-2022 has amounted to NOK 16 billion.
“It goes without saying that this has been a difficult issue for Avinor. On the one hand, we are keen to develop a new airport and we have always been clear about this. The municipality of Bodø is also keen to see a new airport built while also been given the opportunity to build a new neighbourhood. Furthermore, the project has enjoyed broad political support in the Storting. At the same time, this is a very costly project that will have an impact on Avinor’s finances for many years to come. This is a big project for Avinor, the municipality of Bodø and the Norwegian Armed Forces. It is only natural that the path to a final decision has been rather long and winding, even if all parties involved had a clear desire to get it over the finishing line,” says Foss.
Important clarifications
In June 2022, the Board approved its principled endorsement of the airport project, and made it clear that a final decision to proceed with construction would only be made when a number of key aspects of the project were fully clarified.
“We have always been committed to securing the right allocation of costs in the project, and on ensuring that the correct framework with all necessary clarifications is in place between the parties. Now that enough issues have been clarified, we are satisfied to be able to make this historic decision,” he says.
First announcement in January
The first contract to be announced will be published in the first week of January. This will be the contract for the construction of the runway, taxiways, aircraft stands and other external infrastructure, also referred to as ‘contract E02 airside’.
“We are looking forward to getting to work on the project itself and we feel that this decision finally sees us underway. “
“This is a good day for the whole of Nordland county and the town of Bodø. We are really looking forward to working with the municipality and other partners to realise a future-oriented, modern airport,” Foss concludes.
The new Bodø Airport will be located around 900 metres to the south of the present airport. The airport is scheduled to be open and operational in 2029, with its official opening expected in 2029/2030.
The current airport will remain operational until the day before the new airport opens for operations.
Keywords
Contacts
Press service for journalists
We do not answer inquiries between 2100 and 0630 unless there is a critical incident. For info regarding flights - see avinor.no and choose airport.
Images
About The Avinor Group

Dronning Eufemias gate 6
0191 Oslo
+47 67 03 00 00https://avinor.no/en/corporate/about-us/the-avinor-group/about-the-company
Subscribe to releases from The Avinor Group
Subscribe to all the latest releases from The Avinor Group by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from The Avinor Group
Third quarter: Avinor in a strained financial situation for the next few years28.11.2023 16:31:17 CET | Press release
"The Ministry of Transport and Communications stipulates that the basic structure of the company shall remain, but that the financial framework conditions must be strengthened. Avinor appreciates that. At the same time, we expect the financial situation to be strained for the next few years, also with the measures now outlined by the owner," says CEO Abraham Foss.
Traffic figures for October – nearly level with last year10.11.2023 12:00:00 CET | Pressemelding
4.5 million passengers used Avinor's airports in October. This is nearly the same figures as last year, with a slight increase of 1,5 percent. It is 8 percent fewer than in the normal year of 2019.
Traffic figures for September – no year-on-year increase11.10.2023 13:00:00 CEST | Press release
4.5 million passengers used Avinor’s airports in September. This is the same figure as for September last year, but is 10 per cent down on the same month in 2019, which was the last normal year before the pandemic.
Traffic figures for August – more people traveling abroad12.9.2023 12:00:00 CEST | Pressemelding
4.6 million passengers used Avinor’s airports in August. This is an increase of 3 per cent from August last year, but is 6 per cent less than in the same month of 2019.
Cargo to contribute to more intercontinental routes31.8.2023 07:00:00 CEST | Press release
Cargo is an important strategic focus for Avinor. The long-term goal is to enable cargo forwarders to establish their Nordic cargo hub in Norway. Avinor is now appointing a new dedicated Cargo Director while the current postholder transitions to leading Avinor's route development efforts.
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom