Fortuna provides update and sets construction milestones for its Lindero gold Project in Argentina
VANCOUVER, British Columbia, Dec. 21, 2017 (GLOBE NEWSWIRE) -- Fortuna Silver Mines Inc. (NYSE:FSM) (TSX:FVI) is pleased to provide an update on construction activities at its 100 % owned Lindero gold Project located in Salta, Argentina.
Jorge A. Ganoza, President, CEO and Director, commented, "The start of construction activities for a new mine is always an energizing event for an organization." Mr. Ganoza continued, "We are fully funded, key positions in the project team are in place and the Company feels very welcome in the Province of Salta." Mr. Ganoza concluded, "We are looking forward to building and commissioning on time and within budget the first modern large scale precious metals mine in Salta."
In September 2017, the Company announced a positive construction decision for Lindero with commissioning expected in the second quarter of 2019 (see Fortuna news release dated September 21, 2017). Lindero has been designed as an 18,750 tpd1 owner operated open pit mine with a pit life of 13 years based on existing reserves. Crushed ore will be placed on a leach pad with the pregnant solution pumped to SART2 and ADR3 plants prior to electrowining and refining where gold will be poured to doré bars. The technical report of the Lindero Project is available on the Company's website at https://fortunasilver.com/site/assets/files/4098/lindero-project-technical-report-effective-date-31-oct-2017.pdf
With Lindero in its first year of full production, Fortuna's consolidated precious metals annual production is expected to increase to 190,000 ounces of gold and 9 million ounces of silver or 340,000 gold equivalent4ounces.
Note:
- Tonnes per day
- Sulphidization-Acidification-Recycle-Thickening
- Adsorption, Desorption and Recovery
- Gold equivalent is calculated using a gold to silver ratio of 1 to 60 and does not include lead nor zinc
Project Update
In September 2017, the commencement of construction at Lindero was officially launched. As of the end of November, initial contracts have been awarded for approximately US$14 million or 6 percent of the project's capital expenditure.
Detailed Engineering
Engineering, procurement, and construction management (EPCM) was awarded in October 2017 to SAXUM Ingeniería, an Argentinian company with international experience in infrastructure and mining. Detailed engineering work has been launched, procurement packages are being prepared and the bidding process initiated.
Advanced basic engineering of the SART plant is being completed by Kestrel Engineering, an American firm that will work under the direction of Mr. Mike Botz, a qualified engineer with extensive experience of the SART process.
The construction of the leach pad, a critical path of the project, is in the bidding process. Mass earth moving activities are scheduled to commence in February 2018 and are estimated to conclude with the commissioning of the pad in March 2019. Detailed engineering and construction supervision has been awarded to Anddes Argentina, a company specialized in geotechnical engineering and leach pad design and construction.
Mine Equipment
Mine fleet and other heavy equipment are in the process of being awarded. The principal components of the initial mine fleet include six 100 ton trucks, two 17 cubic yard wheel loaders, two bulldozers and two drill rigs.
The Company is evaluating a non-recourse vendor financing of US$15 million for the purchase of mining equipment.
Initial Site Activities
The project requires the upgrading of the existing exploration camp in order to host the initial workforce who will be responsible for building the temporary construction camp. On site activities commenced in November and the temporary facilities will be ready to host the inflow of construction personnel in January 2018. The construction workforce who will build the permanent facilities is estimated to gradually increase and peak at 600 people. The permanent camp facilities will accommodate 320 people.
The Company is in the process of obtaining municipal approval from the town of Tolar Grande for the start of construction activities on new infrastructure. Formal authorization is expected in January 2018.
Project Funding and Financing
The estimated fully scoped capital cost for the construction of Lindero is US$239 million. Capital expenditures are estimated at US$200 million for 2018, and US$36.5 million for 2019; amounts do not include VAT which is expected to be recovered in the first 24 months from the start of mining operations.
The Company plans to fund the construction from a combination of existing cash reserves, projected cash flow generation and an upsized US$120 million credit facility.
Project Construction Milestones
The Company is providing the following selected milestones from the project construction schedule:
2018
- February: Start mass earthworks
- April: First concrete for permanent installations
- August: Start of equipment installation, including HPGR tertiary crusher
- November: Construction of roads and platforms in preparation for initiation of mining activities
2019
- January: Commissioning of power plant
- March: Placing of first ore on the leach pad
- May: First doré poured as part of commissioning
Construction updates will be provided on a regular basis throughout the development of Lindero.
Qualified Person
Eric N. Chapman, Vice President of Technical Services of Fortuna, is the Qualified Person for Fortuna Silver Mines Inc. as defined by National Instrument 43-101. Mr. Chapman is a Professional Geoscientist of the Association of Professional Engineers and Geoscientists of the Province of British Columbia (Registration Number 36328) and is responsible for ensuring that the information contained in this news release is an accurate summary of the original reports and data provided to or developed by Fortuna Silver Mines.
About Fortuna Silver Mines Inc.
Fortuna is a growth oriented, precious metal producer with its primary assets being the Caylloma silver mine in southern Peru, the San Jose silver-gold mine in Mexico and the Lindero gold Project in Argentina. The company is selectively pursuing acquisition opportunities throughout the Americas and in select other areas. For more information, please visit its website at www.fortunasilver.com.
ON BEHALF OF THE BOARD
Jorge A. Ganoza
President, CEO and Director
Fortuna Silver Mines Inc.
Trading symbols: NYSE: FSM | TSX: FVI
Investor Relations:
Carlos Baca
T (Peru): +51.1.616.6060, ext. 0
Forward looking Statements
This news release contains forward looking statements which constitute "forward looking information" within the meaning of applicable Canadian securities legislation and "forward looking statements" within the meaning of the "safe harbor" provisions of the Private Securities Litigation Reform Act of 1995 (collectively, "Forward looking Statements"). All statements included herein, other than statements of historical fact, are Forward looking Statements and are subject to a variety of known and unknown risks and uncertainties which could cause actual events or results to differ materially from those reflected in the Forward looking Statements. The Forward looking Statements in this news release may include, without limitation, statements about the Company's plans for its mines and mineral properties, including the Lindero gold Project; the Company's business strategy, plans and outlook; the merit of the Company's mines and mineral properties; mineral resource and reserve estimates; timelines; the future financial or operating performance of the Company; expenditures; approvals and other matters. Often, but not always, these Forward looking Statements can be identified by the use of words such as "estimated", "potential", "open", "future", "assumed", "projected", "used", "detailed", "has been", "gain", "planned", "reflecting", "will", "containing", "remaining", "to be", or statements that events, "could" or "should" occur or be achieved and similar expressions, including negative variations.
Forward looking Statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any results, performance or achievements expressed or implied by the Forward looking Statements. Such uncertainties and factors include, among others, whether the Company's activities at the Lindero gold Project will proceed as planned; changes in general economic conditions and financial markets; changes in prices for silver and other metals; technological and operational hazards in Fortuna's mining and mine development activities; risks inherent in mineral exploration; uncertainties inherent in the estimation of mineral reserves, mineral resources, and metal recoveries; governmental and other approvals; political unrest or instability in countries where Fortuna is active; labor relations issues; as well as those factors discussed under "Risk Factors" in the Company's Annual Information Form. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in Forward looking Statements, there may be other factors that cause actions, events or results to differ from those anticipated, estimated or intended.
Forward looking Statements contained herein are based on the assumptions, beliefs, expectations and opinions of management, including but not limited to: that the Company's activities at the Lindero gold Project will proceed as planned; expectations regarding mine production costs; expected trends in mineral prices and currency exchange rates; the accuracy of the Company's current mineral resource and reserve estimates; that the Company's activities will be in accordance with the Company's public statements and stated goals; that there will be no material adverse change affecting the Company or its properties; that all required approvals will be obtained; that there will be no significant disruptions affecting operations and such other assumptions as set out herein. Forward looking Statements are made as of the date hereof and the Company disclaims any obligation to update any Forward looking Statements, whether as a result of new information, future events or results or otherwise, except as required by law. There can be no assurance that Forward looking Statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, investors should not place undue reliance on Forward looking Statements.
The issuer of this announcement warrants that they are solely responsible for the content, accuracy and originality of the information contained therein.
Source: Fortuna Silver Mines Inc. via Globenewswire
About GlobeNewswire by notified
GlobeNewswire by notified is one of the world's largest newswire distribution networks, specializing in the delivery of corporate press releases financial disclosures and multimedia content to the media, investment community, individual investors and the general public.
Subscribe to releases from GlobeNewswire by notified
Subscribe to all the latest releases from GlobeNewswire by notified by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from GlobeNewswire by notified
Iveco Group signs a 150 million euro term loan facility with Cassa Depositi e Prestiti to support investments in research, development and innovation11.6.2024 12:00:00 CEST | Press release
Turin, 11th June 2024. Iveco Group N.V. (EXM: IVG), a global automotive leader active in the Commercial & Specialty Vehicles, Powertrain and related Financial Services arenas, has successfully signed a term loan facility of 150 million euros with Cassa Depositi e Prestiti (CDP), for the creation of new projects in Italy dedicated to research, development and innovation. In detail, through the resources made available by CDP, Iveco Group will develop innovative technologies and architectures in the field of electric propulsion and further develop solutions for autonomous driving, digitalisation and vehicle connectivity aimed at increasing efficiency, safety, driving comfort and productivity. The financed investments, which will have a 5-year amortising profile, will be made by Iveco Group in Italy by the end of 2025. Iveco Group N.V. (EXM: IVG) is the home of unique people and brands that power your business and mission to advance a more sustainable society. The eight brands are each a
DSV, 1115 - SHARE BUYBACK IN DSV A/S11.6.2024 11:22:17 CEST | Press release
Company Announcement No. 1115 On 24 April 2024, we initiated a share buyback programme, as described in Company Announcement No. 1104. According to the programme, the company will in the period from 24 April 2024 until 23 July 2024 purchase own shares up to a maximum value of DKK 1,000 million, and no more than 1,700,000 shares, corresponding to 0.79% of the share capital at commencement of the programme. The programme has been implemented in accordance with Regulation No. 596/2014 of the European Parliament and Council of 16 April 2014 (“MAR”) (save for the rules on share buyback programmes set out in MAR article 5) and the Commission Delegated Regulation (EU) 2016/1052, also referred to as the Safe Harbour rules. Trading dayNumber of shares bought backAverage transaction priceAmount DKKAccumulated trading for days 1-25478,1001,023.01489,100,86026:3 June 20247,0001,050.597,354,13027:4 June 20245,0001,055.705,278,50028:6 June20243,0001,096.273,288,81029:7 June 20244,0001,106.174,424,68
Landsbankinn hf.: Offering of covered bonds11.6.2024 11:16:36 CEST | Press release
Landsbankinn will offer covered bonds for sale via auction held on Thursday 13 June at 15:00. An inflation-linked series, LBANK CBI 30, will be offered for sale. In connection with the auction, a covered bond exchange offering will take place, where holders of the inflation-linked series LBANK CBI 24 can sell the covered bonds in the series against covered bonds bought in the above-mentioned auction. The clean price of the bonds is predefined at 99,594. Expected settlement date is 20 June 2024. Covered bonds issued by Landsbankinn are rated A+ with stable outlook by S&P Global Ratings. Landsbankinn Capital Markets will manage the auction. For further information, please call +354 410 7330 or email verdbrefamidlun@landsbankinn.is.
Relay42 unlocks customer intelligence with a new insights and reporting module, powered by Amazon QuickSight11.6.2024 11:00:00 CEST | Press release
AMSTERDAM, June 11, 2024 (GLOBE NEWSWIRE) -- Relay42, a leading European Customer Data Platform (CDP), is leveraging Amazon QuickSight to power its new real-time customer intelligence, reporting, and dashboard module. Harnessing the breadth and quality of customer data, the new Insights module empowers marketing teams to dive deep into customer behaviors and gain invaluable insights into the performance of their marketing programs across all online, offline, paid, and owned marketing channels. Preview of the Relay42 Insights module, in pre-beta version Key capabilities of the Relay42 Insights module include: Deep insights into customer behaviors: With the Relay42 Insights module, marketers can ask unlimited questions about their data and gain a deeper understanding of how to serve their customers more effectively. Simplicity with AI-powered querying: Marketers can use artificial intelligence to query their data using natural language search, reducing the reliance on data scientists. Us
Metasphere Labs Announces X Spaces Event on the Topic of Green Bitcoin Mining and Sound Money for Sustainability11.6.2024 10:30:00 CEST | Press release
VANCOUVER, British Columbia, June 11, 2024 (GLOBE NEWSWIRE) -- Metasphere Labs Inc. (formerly Looking Glass Labs Ltd., "Metasphere Labs" or the "Company") (Cboe Canada: LABZ) (OTC: LABZF) (FRA: H1N) is thrilled to announce an engaging Twitter Spaces event on Green Bitcoin mining, energy markets, and sustainability on July 3, 2024 at 2 p.m. ET. Follow us on X at MetasphereLabs for updates and to join the event. What We'll Discuss Bitcoin Mining Basics: Understand the fundamentals of Bitcoin mining.Energy Market Dynamics: Explore how Bitcoin mining interacts with energy markets.Sustainable Innovations: Learn about our efforts to promote sustainability in Bitcoin mining.Sound Money: Discover how tamper-proof currency can enhance stability.Efficient Payment Rails: See how fast, neutral payment systems support humanitarian projects.Carbon Footprint: Compare Bitcoin's environmental impact with traditional banking. "We're excited to host this event and dive into the critical topics of Bitcoin